HomeMy WebLinkAboutSP-17-06 - Decision - 0006 Lime Rock Road#SP-17-06 CITY OF SOUTH BURLINGTON DEPARTMENT OF PLANNING AND ZONING CHITTENDEN SOLID WASTE DISTRICT — 6 LIME ROCK ROAD SITE PLAN APPLICATION #SP-17-06 FINDINGS OF FACT AND DECISION Chittenden Solid Waste District, hereinafter referred to as the applicant, is seeking to amend a previously approved plan for a 5,000 sq. ft. building consisting of: 1) 2,200 sq. ft. of general office use, and 2) 2,800 sq. ft. of warehouse use. The amendment consists of converting 2,800 sq. ft. of warehouse use to processing & storage use, 6 Lime Rock Road. Based on the plans and materials contained in the document file for this application, the Administrative Officer finds, concludes, and decides the following: FINDINGS OF FACT 1. The applicant is seeking to amend a previously approved plan for a 5,000 sq. ft. building consisting of: 1) 2,200 sq. ft. of general office use, and 2) 2,800 sq. ft. of warehouse use. The amendment consists of converting 2,800 sq. ft. of warehouse use to processing & storage use, 6 Lime Rock Road. 2. The owner of record of the subject property is Stephanie B. Barrett. 3. The subject property is located in the Mixed Industrial -Commercial Zoning District. 4. The application was received on January 31, 2017. 5. The plan submitted is entitled, "S. Barrett, Lime Rock Road South Burlington, Vermont", prepared by P. Carlson, and dated 6/26/00. DIMENSIONAL REQUIREMENTS 6. There are no dimensional changes associated with this application. 7. Setback requirements are being met. SITE PLAN REVIEW STANDARDS Only the standards below are affected by this application. All other standards will continue to be met. - 1 - #SP-17-06 Parking 8. The plan submitted for this application shows six (6) parking spaces available including one (1) handicapped space. The proposed change in use will not require any additional spaces. Parking is located on the front and side of the building. No change to parking is being proposed. 9. The plan does not show a bike rack so the plan will have to be revised to show a bike rack. OTHER 10. The plan does not include the snow storage areas and therefore should be revised to indicate the snow storage areas. DECISION Based on the above Findings of Fact, the Administrative Officer herby approves site plan application #SP-17-06 of Chittenden Solid Waste District, subject to the following conditions: 1) All previous approvals and stipulations which are not superseded by this approval will remain in effect. 2) This project shall be completed as shown on the plan and shall be on file in the South Burlington Department of Planning and Zoning. 3) For the purpose of calculating road impact fees under the South Burlington Impact Fee Ordinance, the Administrative Officer estimates that this project will generate zero (0) additional vehicle trip ends during the p.m. peak hour. 4) The site plan must be revised to show the changes below and will require approval of the Administrative Officer. Three (3) copies of the approved revised plan must be submitted to the Administrative Officer prior to permit issuance. a. The site plan must be revised to show the snow storage areas. b. The site plan must be revised to show a bike rack. 5) The applicant must obtain a zoning permit within six (6) months pursuant to Section 17.04 of the Land Development Regulations or this approval is null and void. 6) Prior to issuance of a zoning permit, the applicant must submit to the Administrative Officer a final set of project plans as approved in digital (PDF) format. 7) All exterior lighting shall be installed or shielded in such a manner as to conceal light sources and reflector surfaces from view beyond the perimeter of the area to WA #SP-17-06 be illuminated. All noncomplying exterior light fixtures must be removed or replaced with conforming fixtures prior to the issuance of a Certificate of Occupancy. 8) The applicant must obtain a Certificate of Occupancy from the Administrative Officer prior to using the building for the new use. 9) Any change to the site plan will require approval by the South Burlington Development Review Board or the Administrative Officer. Signed on this day of /1t / , 2017 by Ravnond I Belair, Admin' rative OfFcer PLEASE NOTE: Pursuant to 24 VSA §4465, an interested person may appeal this decision by filing a Notice of Appeal with the secretary of the Development Review Board. This Notice of Appeal must be accompanied with a $233 filing fee and be filed within 15 days of the date of this decision. The applicant or permittee retains the obligation to identify, apply for, and obtain relevant state permits for this project. Call 802.477-2241 to speak with the regional Permit Specialist. -3-