HomeMy WebLinkAboutSD-01-57 - Decision - 0303 0305 Lime Kiln Road#sD-oi-57
FINDINGS OF FACT AND DECISION
STATE OF VERMONT
COUNTY OF CHITTENDEN
CITY OF SOUTH BURLINGTON
Re: Final plat application of Farwater, Ltd. to amend a planned unit development consisting of
85 residential units in four (4) building and a 42 unit congregate housing facility. The
amendment consists of relocating electrical transformer, bike rack and dumpsters, 303-305 Lime
Kiln Road.
On the 20th of November, 2001, the South Burlington Development Review Board approved the
request of Farwater, Ltd. for final plat approval under Section 204, of the South Burlington Subdivision
Regulations based on the following findings:
1. This project consists of amending a planned unit development consisting of 85 residential
units in four (4) buildings and a 42 unit congregate housing facility. The amendment
consists of relocating electrical transformer, bike rack and dumpsters.
2. The owner of record is Farwater, LTD.
3. This property lies within the Residential Four District. It is bounded on the north and west by
the Winooski River and on the east by the farmlands of John Belter. On the south, a
residence and a commercial structure bound the property. Lime Kiln Road runs through the
middle of the property.
4. The only issues that affect this application are landscaping, dumpster locations and
parking.
5. Landscaping_ The applicant included landscaping to screen the relocated electrical
transformer, which is prominently located in view from the public roadway. Green
Mountain Power required the relocation of the transformer.
6. Parking: The only change to parking is the relocation of the bike rack to a more suitable
location.
7. Dumpsters: The proposed dumpster storage locations are adjacent to the underground parking
entrances. These areas are below grade and not visible from the street.
DECISION AND CONDITIONS
Based on the above Findings of Fact, the South Burlington Development Review Board approves
final plat application #SD-01-57 of Farwater, Ltd. to amend a planned unit development
consisting of 85 residential units in four (4) buildings and a 42 unit congregate housing facility.
The amendment consists of relocating electrical transformer, bike rack and dumpsters, 303-305
Lime Kiln Road., as depicted on an one (1) page set of plans entitled "Farwater LTD Burlington,
Vermont Lime Rock Village Proposed Residential Development Airport Parkway ,South
Burlington, Vermont Partial Site Plan- East Buildings" prepared by Provan and Lorber, Inc., with
the following stipulations:
1) All previous approvals and stipulations which are not superseded by this approval shall remain
in effect.
2) Any change to the plat plan shall require approval by the South Burlington Development Review
Board.
3) The final plat plan shall be recorded in the land records within 90 days or this approval is null
and void. The plan shall be signed by the Board Chair or Clerk prior to recording.
�2-1 o o�
Chair or Clerk f Date
South Burlington Development Review Board
Please Note: You have the right to appeal this decision to the Vermont Environmental Court, pursuant to 24 V.S.A.
§ 4471 and V.R.C.P. 76, in writing, within 30 days of the date this decision is issued. The fee is $150.00. If you fail
to appeal this decision, your right to challenge this decision at some future time may be lost because you waited too
long. You will be bound by the decision, pursuant to 24 V.S.A. § 4472(d) (exclusivity of remedy; finality).
2