CITY OF SOUTH BURLINGTON
DEPARTMENT OF PLANNING AND ZONING
FARRELL DISTRIBUTING CORPORATION — 5 HOLMES ROAD
SITE PLAN APPLICATION #SP-15-10
FINDINGS OF FACT AND DECISION
Site plan application #SP-15-10 of Farrell Distributing Corporation to amend a previously approved plan
for 138,660 sq. ft. warehouse & distribution facility for a wholesale business. The amendment consists
of: 1) constructing a 25,316 sq. ft. addition, 2) constructing a new 576 sq. ft. gas fueling canopy, 3)
constructing a second story 1339 sq. ft. deck with outside stairs, and 4) site modifications, 5 Holmes
Road.
The Development Review Board held a public hearing on April 7, 2015 and April 21, 2015. Steve Vock &
Todd Bouton represented the applicant.
Based on testimony provided at the above mentioned public hearing and the plans and supporting
materials contained in the document file for this application, the Development Review Board finds,
concludes, and decides the following:
FINDINGS OF FACT
1. Farrell Distributing Corporation, hereafter applicant, is requesting site plan review to amend a
previously approved plan for 138,660 sq. ft. warehouse & distribution facility for a wholesale
business. The amendment consists of: 1) constructing a 25,316 sq. ft. addition, 2) constructing a
new 576 sq. ft. gas fueling canopy, 3) constructing a second story 1339 sq. ft. deck with outside
stairs, and 4) site modifications, 5 Holmes Road.
2. The owners of record of the subject property are D. M. Farrell & S. McConaughy.
3. The application was submitted on March 24, 2015
4. The subject property is located in the Commercial 2 Zoning District.
5. The plans submitted consist of a thirty-five (35) page set of plans, page one (1) entitled, "Farrell
Distributing Illustrative Plan South Burlington, VT", prepared by T.J. Boyle Associates, with a
stamped received date of April 9, 2015.
Zoning District & Dimensional Requirements:
Commercial 2 Zoning District
Min. Lot Size
Required
40,000 S.F.
Existing
584,148 s.f.
Proposed
584,148 s.f.
Max. Building Coverage
40%
25.9%
29.9 %
Max. Overall Coverage
70%
55.9%
61.9 %
Max. Front Yard Coverage
30%
12.7%
24.6 %
Min. Front Setback
30 ft
> 30 ft
338 ft
Min. Side Setback
10 ft.
> loft.
68 ft.
- 1 —
#SP-15-10
L�1 Min. Rear Setback 30 ft. > 30 ft. 35 ft.
Max. Buildine Height 40 ft. < 40 ft. 28 ft.
Zoning Compliance
Site Plan Review Standards
A. Relationship of Proposed Development to the City of South Burlington Comprehensive Plan.
Due attention by the applicant should be given to the goals and objectives and the stated land use
policies for the City of South Burlington as set forth in the Comprehensive Plan.
The Board finds the proposed building and uses to be consistent with the Comprehensive Plan.
B. Relationship of Proposed Structures to the Site.
(1) The site shall be planned to accomplish a desirable transition from structure to site, from
structure to structure, and to provide for adequate planting, safe pedestrian movement, and
adequate parking areas.
Existing parking at the site is divided as follows: existing spaces are 58 truck spaces and 109 car spaces
while proposed parking is 37 truck spaces and 133 car spaces. Based upon a proposed final square
footage of 175,000 SF of predominantly warehouse space, 88 car parking spaces are required. This
requirement is met.
The Board finds that this criterion has been met.
2) Parking:
(a) Parking shall be located to the rear or sides of buildings. Any side of a building facing a
public street shall be considered a front side of a building for the purposes of this subsection.
(b) The Development Review Board may approve parking between a public street and one
or more buildings if the Board finds that one or more of the following criteria are met. The
Board shall approve only the minimum necessary to overcome the conditions below.
(i) ...............
(ii) ..............
ON ...............
(iv) The lot contains one or more existing buildings that are to be re -used and parking
needs cannot be accommodated to the rear and sides of the existing building(s);
The Board recognizes the goal of the applicant to improve safety on the property by creating a new
truck only curb cut and segregating the flow of truck traffic and employee traffic and parking. Vehicle
parking areas have been maximized in areas away from truck traffic. Given the existing conditions on the
site and improvements to be made, the Board finds that the proposal meets condition (iv) noted above.
(v) ...........................
NO........................
(c)
................................
-2—
#SP-15-10
(d).................................
(3) Without restricting the permissible limits of the applicable zoning district, the height and
scale of each building shall be compatible with its site and existing or anticipated adjoining
buildings.
The proposed addition is 28 ft. high and similar in size to other buildings on the lot. The Board finds
that this criterion to be met.
(4) Newly installed utility services and service modifications necessitated by exterior
alterations or building expansion shall, to the extent feasible, be underground.
The plans indicate that such services are located underground. The Board finds that this criterion
has been met.
C. Relationship of Structures and Site to Adjoining Area.
(1) The Development Review Board shall encourage the use of a combination of common
materials and architectural characteristics (e.g., rhythm, color, texture, form or detailing),
landscaping, buffers, screens and visual interruptions to create attractive transitions between
buildings of different architectural styles.
A rear addition to the property's main building is proposed as well as other improvements. As noted
above, the applicant has submitted a landscaping plan which the City Arborist found acceptable with
the exception of a minor detail. The Board finds that this criterion has been met.
(2) Proposed structures shall be related harmoniously to themselves, the terrain and to
existing buildings and roads in the vicinity that have a visual relationship to the proposed
structures.
The proposed addition, gas canopy and deck are consistent with the surrounding landscape and with
others in the vicinity. The Board finds that this criterion has been met.
14.07 Specific Review Standards
A. Access to Abutting Properties. The reservation of land may be required on any lot for provision
of access to abutting properties whenever such access is deemed necessary to reduce curb cuts onto
an arterial or collector street, to provide additional access for emergency or other purposes, or to
improve general access and circulation in the area.
No reservation of land is required.
B. Utility Services. Electric, telephone and other wire -served utility lines and service connections
shall be underground insofar as feasible and subject to state public utilities regulations. Any utility
installations remaining above ground shall be located so as to have a harmonious relation to
neighboring properties and to the site.
The plans indicate that such services are located underground. The Board finds that this criterion has
been met.
-3—
#SP-15-10
C. Disposal of Wastes. All dumpsters and other facilities to handle solid waste, including
compliance with any recycling or other requirements, shall be accessible, secure and properly screened
with opaque fencing to ensure that trash and debris do not escape the enclosure(s). Small receptacles
intended for use by households or the public (ie, non-dumpster, non -large drum) shall not be required
to be fenced or screened.
The plans show a proposed location for a concrete pad to site a trash compactor which will be enclosed.
The Board finds that this criterion has been met.
D. Landscaping and Screening Requirements. See Article 13, Section 13.06 Landscaping,
Screening, and Street Trees.
Building construction cost is estimated at $1,658,719. Required minimum landscaping is calculated as
follows:
First $250,000 x 3% _ $7,500
Next 250,000 x 2% _ $5,000
Balance over $500,000 x 1% _ $11,587
Minimum required landscaping budget = $23,587.
The applicant is proposing to remove many existing trees on the property, however. The applicant met with
the City Arborist to discuss how to replace the proposed trees to be removed and sent the following email
to staff on April 9, 2015 outlining the details of their agreement along with a revised landscaping plan and
schedule.
Ray,
Per our phone conversation, I met with Craig Lambert at the Farrell Distributing site this and we came to
an agreement on proposed tree replacements. I've attached the revised demo plan, landscape plan and
planting estimate. I'll follow up in a separate email with the rendering, and will stop by to drop off the
hard copies today.
In summary of our meeting, there will be a 2 to 1 replacement ratio (two new trees to replace each
single tree removed). Conversely, there is a 1 to 2 ratio for the diameter inch replacement (69.5" to
replace the existing 140"). In particular, we're proposing additional trees immediately east of the
building as well as further up the hill, and we will remove the remaining white pines in the parking area
so as to fit in additional hardwoods. I've included some of Craig's suggestions on species, and
replacement tree plantings are highlighted in green on the attached landscape plan.
Thanks to you and Craig for working with us on this, and please stay tuned for the updated rendering.
Jeremy
JEREMY B. OWENS, PLA
Associate Landscape Architect
#SP-15-10
T. I. Boyle Associates, ttC
In total, the applicant is proposing a final planting cost of $45,157.05 with the "trees and shrubs" portion of
the landscaping costs amounting to $43,350.00.
The Board finds that this criterion is met.
E. Modification of Standards. Where the limitations of a site may cause unusual hardship in
complying with any of the standards above and waiver therefrom will not endanger the public health,
safety or welfare, the Development Review Board may modify such standards as long as the general
objectives of Article 14 and the City's Comprehensive Plan are met. However, with the exception of
side yard setbacks in the Central District 1, in no case shall the DRB permit the location of a new
structure less than five (5) feet from any property boundary and in no case shall be the DRB allow land
development creating a total site coverage exceeding the allowable limit for the applicable zoning
district in the case of new development, or increasing the coverage on sites where the pre-existing
condition exceeds the applicable limit.
No waivers are required.
STORMWATER
The Public Works Department provided the following comments to staff on April 7, 2015
Ray,
I reviewed the "Farrell Distributing Corp. " site plan for the property located at 5 Holmes Road, prepared
by Civil Engineering Associates, dated 2125115 and last updated on 2125115. l would like to offer the
following comments:
1. The proposed project is located outside of the City's stormwater impaired watersheds in on area
that discharges directly into Shelburne Bay via an unnamed stream.
2. The applicant should confirm that the dimensional summary tables provided on sheet C2.0
accurately list the proposed dimensions.
3. The project will require a construction stormwater permit from the Vermont DECStormwater
Division if greater than 1 acre of land is disturbed. If necessary, the applicant should acquire this
permit before starting construction.
4. The property is covered by an existing State stormwater permit issued by Vermont DEC. The
proposed increase in impervious area will require an update to this existing State permit. The
applicant should provide information regarding the status of this State permit application.
5. The applicant should provide drainage area maps and hydrologic modeling (the same modeling
that was submitted to DEC is sufficient) for all new or improved stormwoter treatment practices.
-5—
r
#SP-15-10
6. Water drains from this site to the west and reaches the lake after passing through a culvert under
the railroad and a culvert under the driveway for an adjacent property. The applicant should
confirm that these culverts can safely pass the 25 year storm event under proposed conditions. This
is a requirements of section 15.13.F(3) of the City's Land Development Regulations.
7. The applicant should show snow storage locations on the site plan.
8. The DRB should include a condition requiring the applicant to regularly maintain all stormwater
treatment and conveyance infrastructure.
Thank you for the opportunity to comment.
-Tom
Thomas J. Di Pietro Jr.
Deputy Director
Department of Public Works
The applicant responded to the above comments on April 17, 2015 and Mr. DiPietro responded on April
20, 2015 that he had no further comment.
The Board finds that the applicant shall comply with the recommendations of the Department of Public
Works.
FIRE DEPARTMENT COMMENTS
In an email to staff dated March 25, 2015 the Fire Chief provided the following comments:
Dear Ray:
Myself and Deputy Chief Francis have reviewed the site plans for Farrell
Distributing at 5 Holmes Road. This is for their proposed expansion project. We have the following
comments:
1. The fire hydrant relocation plans are good.
2. Fire Department access is good.
3. Landscaping plan does not seem to interfere with fire department access and
Emergency equipment deployment.
4. Building plans should be approved by the South Burlington Fire Marshal prior to any
construction.
Should you need any further assistance on this project please feel free to contact me.
l�
#SP-15-10
Sincerely,
Douglas S. Brent
Fire Chief
The Board finds that the applicant shall comply with the recommendations of the Fire Chief.
Traffic Generation
Based upon a final construction total of a 175,000 SF of predominantly warehouse building (ITE LUC
#110), the weekday PM Peak Hour average vehicle trip ends is calculated as follows: 0.32 (trip
generation per 1,000 SF g.f.a.) x 175 = estimated number of vehicle trip ends generated by current uses
is 87.5 trip ends.
The property's current allocation of trip ends is 153 VTEs as established in a prior Findings of Fact &
Decision signed on February 25, 1997.
The Board therefore finds that no additional traffic is expected from the expansion.
DECISION
Motion by John Wilking, seconded by David Parsons, to approve Site Plan Application #SP-15-10 of
Farrell Distributing Corporation, subject to the following conditions:
All previous approvals and stipulations, which are not superseded by this approval, shall remain
in effect.
2. This project shall be completed as shown on the plans submitted by the applicant and on file in
the South Burlington Department of Planning and Zoning.
3. The plans shall be revised to show the changes below and shall require approval of the
Administrative Officer. Three (3) copies of the approved revised plans shall be submitted to the
Administrative Officer prior to permit issuance.
The plans shall be revised to comply with the comments of the City of South Burlington
Department of Public Works per the email dated April 7, 2015.
4. The proposed project shall adhere to standards for erosion control as set forth in Section 16.03 of
the South Burlington Land Development Regulations. In addition, the grading plan should meet the
standards set forth in Section 16.04 of the South Burlington Land Development Regulations. The
South Burlington Stormwater Superintendent shall visit the site as construction progresses to
ensure compliance with this criterion.
5. The applicant shall regularly maintain all stormwater treatment and conveyance infrastructure.
-7—
#SP-15-10
6. For the purpose of calculating road impact fees under the South Burlington Impact Fee Ordinance,
the Development Review Board estimates that the proposed expansion will generate a total of zero
(0) additional vtes.
7. Pursuant to Section 15.13(E) of the Land Development Regulations, any new utility lines, services,
and service modifications should be underground.
8. Prior to zoning permit issuance for construction of the project, the applicant shall post a $43,350
landscaping bond. This bond shall remain in full effect for three (3) years to assure that the
landscaping has taken root and has a good chance of survival.
9. The applicant shall obtain a zoning permit within six (6) months pursuant to Section 17.04 of the
Land Development Regulations or this approval is null and void.
10. All exterior lighting shall be downcast and shielded, and otherwise comply with Section 13.07 of
the SBLDR.
11. Prior to issuance of a zoning permit for the addition, the applicant shall submit to the
Administrative Officer a final set of project plans as approved in digital (PDF) format.
12. The applicant shall obtain a Certificate of Occupancy from the Administrative Officer prior to the
use of the addition.
13. Any change to the site plan shall require approval of the South Burlington Development Review
Board or the Administrative Officer.
Tim Barritt
Yea Nay
Abstain
Not Present
Mark Behr
Yea Nay
Abstain
Not Present
Brian Breslend
Yea Nay
Abstain
Not Present
Bill Miller
Yea Nay
Abstain
Not Present
David Parsons
Yea Nay
Abstain
Not Present
Jennifer Smith
Yea Nay
Abstain
Not Present
John Wilking
Yea Nay
Abstain
Not Present
Motion carried by a vote of 6— 0 — 0.
1 'I
Signed this
day of I
2015, by
im Barritt, Chair
Please note: You have the right to appeal this decision to the Vermont Environmental Court, pursuant
to 24 VSA 4471 and VRCP 76 in writing, within 30 days of the date this decision is issued. The fee is
$225.00. If you fail to appeal this decision, your right to challenge this decision at some future time may
be lost because you waited too long. You will be bound by the decision, pursuant to 24 VSA 4472 (d)
(exclusivity of remedy; finality).