Loading...
HomeMy WebLinkAboutSP-16-72 - Decision - 0041 Rye Circle#SP-16-72 CITY OF SOUTH BURLINGTON DEPARTMENT OF PLANNING & ZONING RYE ASSOCIATES, LLC — 41 RYE CIRCLE SITE PLAN APPLICATION #SP-16-72 FINDINGS OF FACT AND DECISION Rye Associates, LLC, hereinafter referred to as the applicant, is seeking site plan approval to amend a previously approved plan for a 4,726 sq. ft. general office building (not yet constructed). The amendment consists of relocating a handicapped space, 41 Rye Circle. Based on the findings below, the Administrative Officer finds, concludes, and decides the following: FINDINGS OF FACT 1. The applicant is seeking site plan approval to amend a previously approved plan for a previously approved plan for a 4,726 sq. ft. general office building (not yet constructed). The amendment consists of relocating a handicapped space, 41 Rye Circle. 2. The owner of record of the subject property is Rye Associates, LLC. 3. The subject property is located in the Southeast Quadrant Village Commercial Zoning District. 4. The application was received on October 14, 2016. 5. The plan set submitted consists of seven (7) pages, page one (1) is entitled, "Rye Meadow Commercial Development 1075 Hinesburg Rd. South Burlington Vermont" prepared by Civil Engineering Associates, Inc., dated February 2016, and last revised on 9/28/16. DIMENSIONAL REQUIREMENTS 6. All dimensional requirements will continue to be met. SITE PLAN REVIEW STANDARDS Only the standards below will are affected by this application. All other standards will continue to be met. -1- #SP-16-72 Parking 7. One (1) handicapped space will relocated from the north side of the building to the south side of the building. No change in the number of spaces being provided. Snow Storage 8. The plans do not depict the snow storage area(s) as required. Therefore, the plans will have to be revised to show the snow storage area(s). DECISION Based on the above Findings of Fact, the Administrative Officer hereby approves site plan #SP-16-72 of Rye Associates, LLC, based on the following conditions: 1. All previous approvals and stipulations which are not superseded by this approval will remain in effect. 2. This project must be completed as shown on the plan and will be on file in the South Burlington Department of Planning and Zoning. 3. The site plan must be revised to show the changes below and will require approval of the Administrative Officer. Three (3) copies of the approved revised plan must be submitted to the Administrative Officer prior to permit issuance. a. The site plan must be revised to show the snow storage area(s). 3. The applicant must obtain a zoning permit within six (6) months pursuant to Section 17.04 of the Land Development Regulations or this approval is null and void. 4. The Applicant must obtain a Certificate of Occupancy from the Administrative Officer prior to the use of the new parking layout. 5. Prior to issuance of a zoning permit, the applicant must submit to the Administrative Officer a final set of project plans as approved in digital (PDF) format. 6. Any change to the site plan shall require approval by the South Burlington Administrative Officer or the Development Review Board. -2- #SP-16-72 Signed on this4;� day of 2016 by mond J. Belair, Admirwrative Officer PLEASE NOTE: Pursuant to 24 VSA §4465, an interested person may appeal this decision by filing a Notice of Appeal with the secretary of the Development Review Board. This Notice of Appeal must be accompanied with a $233 filing fee and be filed within 15 days of the date of this decision. The applicant or permittee retains the obligation to identify, apply for, and obtain relevant state permits for this project. Call 802.879.5676 to speak with the regional Permit Specialist. -3-