CITY OF SOUTH BURLINGTON
DEPARTMENT OF PLANNING AND ZONING
GARDNER CONSTRUCTION- 22 & 30 HIGHLAND TERRACE
FINAL PLAT APPLICATION #SD-10-35
FINDINGS OF FACT AND DECISION
Gardner Construction, Inc. is seeking final plat approval to amend a previously approved three
(3) lot subdivision. The amendment consists of connecting two (2) of the lots to the City's sewer
system in place of on -site septic systems, 22 & 30 Highland Terrace.
The Development Review Board held public hearings on December 7, 2010, January 4, and
May 17, 2011. Brad Gardner represented the applicant.
Based on testimony provided at the above mentioned public hearing and the plans and
supporting materials contained in the document file for this application, the Development
Review Board finds, concludes, and decides the following:
FINDINGS OF FACT
1. Gardner Construction, Inc. is seeking final plat approval to amend a previously approved
three (3) lot subdivision. The amendment consists of connecting two (2) of the lots to the City's
sewer system in place of on -site septic systems, 22 & 30 Highland Terrace.
2. The owner of record of the subject property is Gardner Construction Inc.
3. The application was received on November 12, 2010.
4. The subject property is located in the Southeast Quadrant Zoning District.
5. The plans submitted consist of a two (2) page set of plans, page one (1) entitled "Site Plan
Gardner Construction Inc, Revision to ww-4-2773 for Connection to Municipal Sewer Highland
Terrace South Burlington, VT", prepared by McCain Consulting Inc, dated 4/26/11.
The applicant is seeking to connect the proposal to municipal wastewater rather than on -site
septic. The Director of Public Works has reviewed the plans and has stated that they are
acceptable. The only comment is that the applicant shall provide a mechanism for monitoring
wastewater usage for sewer billing. Most wastewater billing is based on water usage; as the
subject property will be utilizing well -water, the property will require a separate meter.
I91x6164IQ I,
Motion by Gavle Quimby, seconded by Roger Farley, to approve Final Plat Application #SD-
10-35 of Gardner Construction Inc, subject to the following conditions:
1. All previous approvals and stipulations shall remain in full effect except as amended herein.
CADocuments and Settings\Mark C. Behr\My Documents\South Burlington DRB\5.17.11 Meeting
Decisions\SD_10_35_HighlandTerrace_Gardner.doc
#SD-10-33
2. This project shall be completed as shown on the plat submitted by the applicant and on file
in the South Burlington Department of Planning and Zoning.
3. The applicant shall propose and install a mechanism for monitoring sewage usage. This
mechanism must be approved by the Director of Public Works and installed prior to
occupancy of the residence.
4. Any changes to the final plat plan shall require approval of the South Burlington
Development Review Board.
5. The final plat plan (sheet 1 of 2) shall be recorded in the land records within 180 days or this
approval is null and void. The plan shall be signed by the Board Chair or Clerk prior to
recording. Prior to recording the final plat plan, the applicant shall submit a copy of the
survey plat in digital format. The format of the digital information shall require approval of the
South Burlington GIS Coordinator.
Mark Behr — yea/nay/abstain/not present
Matthew Birmingham — yea/nay/abstain/not present
John Dinklage — yea/nay/abstain/not present
Roger Farley — yea/nay/abstain/not present
Michael Sirotkin — yea/nay/abstain/not present
Gayle Quimby — yea/nay/abstain/not present
Bill Stuono — yea/nay/abstain/not present
Motion carried by a vote of 4 — 0 — 0
Signed this 18th day of May 2011, by
Digitally signed by Mark C, Behr
Mark C . Behr Architect
ite Mark C Behr, it Richard Henry Behr
Architect P.C., ou,email=mark@rhbperom, -US
Date: 2011.05.18 09:35:22 -04,0'
Mark Behr, Chairman
Please note: An appeal of this decision may be taken by filing, within 30 days of the date of
this decision, a notice of appeal and the required fee by certified mail to the Superior Court,
Environmental Division. See V.R.E.C.P. 5(b). A copy of the notice of appeal must also be
mailed to the City of South Burlington Planning and Zoning Department at 575 Dorset Street,
South Burlington, VT 05403. See V.R.E.C.P. 5(b)(4)(A). Please contact the Environmental
Division at 802-828-1660 or httr):Hvermontiuda icia[y.orcl/GTC/environmental/default.asr)x for
more information on filing requirements, deadlines, fees and mailing address.
The applicant or permittee retains the obligation to identify, apply for, and obtain relevant state
permits for this project. Call 802.879.5676 to speak with the regional Permit Specialist.