CITY OF SOUTH BURLINGTON
DEPARTMENT OF PLANNING AND ZONING
ROBERT PARK - MDT PARTNERSHIP - 9 GREEN MOUNTAIN DRIVE
SITE PLAN APPLICATION #SP-06-21
FINDINGS OF FACT AND DECISION
Robert Park, hereafter referred to as the applicant, is seeking site plan approval to
amend a previously approved plan for an 11,200 sq. ft. automotive repair and sales
facility at 5 Green Mountain Drive and an 11,925 sq. ft. automotive repair building at 9
Green Mountain Drive. The amendment consists of converting 3150 sq. ft. of automotive
repair use to retail use, 9 Green Mountain Drive. The Development Review Board held
a public hearing on May 16, 2006. The applicant was present at the meeting.
Based on testimony provided at the above mentioned public hearing and the plans and
supporting materials contained in the document file for this application, the Development
Review Board finds, concludes, and decides the following:
FINDINGS OF FACT
The applicant is seeking site plan approval to amend a previously approved plan
for an 11,200 sq. ft. automotive repair and sa►es facility at 5 Green Mountain
Drive and an 11,925 sq. ft. automotive repair building at 9 Green Mountain Drive.
The amendment consists of converting 3150 sq. ft. of automotive repair use to
retail use, 9 Green Mountain Drive.
2. The owner of record of the subject property is MDT Partnership.
3. The subject property is located in the Commercial 2 (C2) Zoning District.
4. The plan submitted is entitled, "Proposed Addition & New Building Mark Hill
Investments, Inc.", prepared by Forest/Teychmacher, Architects, dated 12/5/83,
with a stamped received date of 4/13/06.
O-RV3\ 1 0(0
- 1 -
#S P-06-21
Zoning District & Dimensional Requirements:
Table 1. Dimensional Requirements
C2 Zoning District
Required
Proposed
4 Min. Lot Size
40,000 SF
90,000 SF
Max. Building Coverage
40%
26%
Max. Overall Coverage
70%
67%
Max. Front Yard Coverage
30%
27%
�l Min. Front Setback
30'
>30
Min. Side Setback
101,
>10'
Min. Rear Setback
30'
>30'
�I Zoning compliance
SITE PLAN REVIEW STANDARDS
Section 14.06 of the South Burlington Land Development Regulations establishes the
following general review standards for all site plan applications:
(a) The site shall be planned to accomplish a desirable transition from structure
to site, from structure to structure, and to provide for adequate planting, safe
pedestrian movement, and adequate parking areas.
No changes to the existing buildings are being proposed as part of this application.
However staff finds that this criterion is being met.
Given the proposed use of 8775 square feet of auto repair and 3150 square feet of retail
sales on the property, 34 spaces are required. The site plan depicts 24 spaces. However,
the applicant has stated that the use of the retail sales will be an auction business whose
operating hours will not be from 7-5 pm, Monday through Friday. The auction business will
only operate after 6 pm on week days and various hours on the weekends. Because the
auto repair businesses in the building will close before the auction business will open, the
site will be utilizing shared parking. This is acceptable. There are enough spaces for each
use independently (18 spaces for auto repair and 16 for retail sales).
(b) Parking shall be located to the rear or sides of buildings to the greatest extent
practicable.
No changes to the existing buildings are being proposed as part of this application.
However staff finds that this criterion is mostly being met.
(c) Without restricting the permissible limits of the applicable zoning district, the
height and scale of each building shall be compatible with its site and
existing or adjoining buildings.
The height of the building will remain unchanged at 35 feet.
WA
#S P-06-21
(d) Newly installed utility services and service modifications necessitated by
exterior alterations or building expansions shall, to the extent feasible, be
underground.
No changes to the existing buildings are being proposed as part of this application.
Pursuant to Section 15.13(E) of the Land Development Regulations, any new utility
lines, services, and service modifications shall be underground.
(e) The DRB shall encourage the use of a combination of common materials and
architectural characteristics, landscaping, buffers, screens and visual
interruptions to create attractive transitions between buildings of different
architectural styles.
The proposed project does not involve any new exterior construction, so this criterion is not
applicable.
(t) Proposed structures shall be related harmoniously to themselves, the terrain,
and to existing buildings and roads in the vicinity that have a visual
relationship to the proposed structures.
The proposed project does not involve any new exterior construction, so this criterion is not
applicable.
Site plan applications shall meet the following specific standards as set forth in Section
14.07 of the South Burlington Land Development Regulations:
(a) The reservation of land may be required on any lot for provision of access to
abutting properties whenever such access is deemed necessary to reduce
curb cuts onto an arterial of collector street, to provide additional access for
emergency or other purposes, or to improve general access and circulation
in the area.
The Board does not suggest providing additional accesses.
(b) Electric, telephone and other wire -served utility lines and service connections
shall be underground. Any utility installations remaining above ground shall
be located so as to have a harmonious relation to neighboring properties and
to the site.
Pursuant to Section 15.13(E) of the Land Development Regulations, any new utility lines,
services, and service modifications shall be underground.
(c) All dumpsters and other facilities to handle solid waste, including compliance
with any recycling or other requirements, shall be accessible, secure and
properly screened with opaque fencing to ensure that trash and debris do not
escape the enclosure(s).
There are existing dumpsters on the site that are adequately screened.
-3-
#S P-06-21
(d) Landscaping and Screening Requirements
As there is no building construction proposed for this site, there are no minimum
landscaping requirements.
Pursuant to Section 13.06(B) of the Land Development Regulations, the plans shall
depict snow storage areas that will minimize the potential for run-off. No snow storage
areas are shown on the plans.
Lighting
Pursuant to Section 13.07(A) of the Land Development Regulations, all exterior lighting
shall be shielded and downcasting to prevent light from spilling onto adjacent properties
and rights -of -way. The applicant has stated that there is no new lighting proposed as
part of this application.
DECISION
Motion by k4L Qu1h16 ' , seconded by /t�
to approve Site Plan Application SP-06-21 of Robert Park, subject to the following
conditions:
1) All previous approvals and stipulations, which are not superseded by this approval,
shall remain in effect.
2) This project shall be completed as shown on the plans submitted by the applicant, as
amended herein, and on file in the South Burlington Department of Planning &
Zoning.
3) The plans shall be revised to show the changes below and shall require approval of
the Administrative Officer. Three (3) copies of the approved revised plans shall be
submitted to the Administrative Officer prior to permit issuance.
a) The plans shall be revised to depict adequate snow storage areas.
b) The plans shall be revised to remove all references to the formerly proposed new
buildings, driveways, and parking areas. No new buildings, driveways, or parking
areas are being considered as part of this proposal.
c) The plans shall be revised to depict a bicycle rack in compliance with Section
13.01(G)(5) of the Land Development Regulations.
4) The applicant shall obtain a zoning permit within six (6) months pursuant to Section
17.04 of the Land Development Regulations or this approval is null and void.
-4-
#SP-06-21
5) The applicant shall obtain a Certificate of Occupancy/Compliance from the
Administrative Officer prior to the use of the newly converted space.
6) Any change to the site plan shall require approval by the South Burlington
Development Review Board.
Mark Behr — e�nay/abstain/not present
Matthew Birmingham — yea/nay/abstain/not present
Chuck Bolton — iea/nay/abstain/nooresent
John Dinklage — yea/nay/abstain not present
Roger Farley — yea/nay/abstaintnot present
Larry Kupferman — yea/nay/abs am/not present
Gayle Quimby — yea/nay/abstain/not present
Motion carried by a vote of -%-_
Signed this day of ►"'tAV 2006, by
Mark Behr, Vice Chairman
Please note: You have the right to appeal this decision to the Vermont Environmental
Court, pursuant to 24 VSA 4471 and VRCP 76 in writing, within 30 days of the date this
decision is issued. The fee is $225.00. If you fail to appeal this decision, your right to
challenge this decision at some future time may be lost because you waited too long.
You will be bound by the decision, pursuant to 24 VSA 4472 (d) (exclusivity of remedy;
finality).