Re: Findings of Fact, application of South Burlington Little League to amend a previously approved
plan for Dorset Street Park. The amendment consists of: 1) the construction of a 576 square foot
concession stand, and 2) the erection of three (3) scoreboards, 1000 Dorset Street.
On the day of May, 1999, the South Burlington Director of Planning & Zoning approved the
request of South Burlington Little League for site plan review under Section 26.10 of the South
Burlington Zoning Regulations based on the following findings:
1. This project consists of amending a previously approved plan for Dorset Street Park. The
amendment consists of ]) the construction of a 576 square foot concession stand, and 2) the erection
of three (3) scoreboards. The only issues affected by this application are coverage, setbacks, and
landscaping.
2. The owner of record of this particular property is the City of South Burlington.
3. Coverage/setbacks: Building coverage is 2% (maximum allowed is 30%). Overall coverage is
10.9% (maximum allowed is 70%). Front yard coverage along Dorset Street is 0% and front yard
coverage along Swift Street Extension is 5.1 % (maximum allowed is 30%).
Setback requirements are met.
4. Landscaping: The minimum landscaping requirement, based on building costs, is $45 which is
being met. Proposed landscaping consists of Yew and Arborvitae.
5. Sim The scoreboards are proposed to include signage. This request does not include signage.
DECISION & CONDITIONS
Based on the above Findings of Fact, the South Burlington Director of Planning & Zoning approves
the site plan application of South Burlington Little League to amend a previously approved plan for
Dorset Street Park. The amendment consists of: 1) the construction of a 576 square foot concession
stand, and 2) the erection of three (3) scoreboards, 1000 Dorset Street, as depicted on a plan
entitled," Planting Plan Dorset Street Park - Phase I City of South Burlington South Burlington
Vermont," prepared by Thermo Consulting Engineers, dated August, 1995, with a stamped received
date of April 21, 1999, with the following stipulations:
1) All previous approvals and stipulations which are not superseded by this approval shall remain in
effect.
2. The applicant shall obtain a zoning permit within six (6) months pursuant to Section 27.302 of
the zoning regulations or this approval is null and void.
3. The applicant shall obtain a Certificate of Occupancy/Compliance from the Administrative Officer
prior to the use of the concession stand and scoreboards.
4. Any change to the site plan shall require approval by the South Burlington Planning Commission.
South Burliogton Director of Planning & Zoning