The South Burlington School District, hereafter referred to as the applicant, is seeking
site plan approval to amend a previously approved plan for an educational facility
complex consisting of a high school and middle school. The amendment consists of: 1)
eliminating a previously approved but not constructed 1,600 sq. ft. team room building
and 2) altering sidewalks and landscaping, 550 Dorset Street.
Based on the plans and materials contained in the document file for this application, the
Administrative Officer finds, concludes, and decides the following:
FINDINGS OF FACT
1. The applicant is seeking site plan approval to amend a previously approved plan for
an educational facility complex consisting of a high school and middle school. The
amendment consists of: 1) eliminating a previously approved but not constructed 1,600
sq. ft. team room building and 2) altering sidewalks and landscaping, 550 Dorset Street.
2. The application was received on January 26, 2011.
3. The owner of record of the subject property is the South Burlington School District
4. The subject property is located in the Municipal Zoning District.
5. The plans submitted consist of a one (1) page plan entitled, "Site Plan South
Burlington High School Concession Building 500 Dorset Street South Burlington,
Vermont", prepared by Summit Engineering, Inc., dated 11/23/2010.
Zoning District & Dimensional Requirements:
The elimination of this building will return the total overall coverage to 13.8%, well within
the limits of the district.
SITE PLAN REVIEW STANDARDS
Section 14.06 of the South Burlinqton Land Development Regulations establishes the
following general review standards for all site plan applications:
(a) The site shall be planned to accomplish a desirable transition from
structure to site, from structure to structure, and to provide for adequate
planting, safe pedestrian movement, and adequate parking areas.
The applicant proposes the installation of an additional 307 sq. ft. of sidewalks to support
existing structures.
FAUSERS\Planning & Zoning\Development Review Board\Findings_Decisions\2011\SP_11_05_550
Dorset_SBSD_ffd.doc
#SP-11-05
(b) Parking shall be located to the rear or sides of buildings to the greatest
extent practicable.
(c) Without restricting the permissible limits of the applicable zoning district,
the height and scale of each building shall be compatible with its site and
existing or adjoining buildings.
(d) Newly installed utility services and service modifications necessitated by
exterior alterations or building expansions shall, to the extent feasible, be
underground.
(e) The DRB shall encourage the use of a combination of common materials
and architectural characteristics, landscaping, buffers, screens and visual
interruptions to create attractive transitions between buildings of different
architectural styles.
(t) Proposed structures shall be related harmoniously to themselves, the
terrain, and to existing buildings and roads in the vicinity that have a visual
relationship to the proposed structures.
The elimination of the approved but not constructed 1,600 sq. ft. team room building will
retain site conditions as they presently as related to buildings.
Site plan applications shall meet the following specific standards as set forth in Section
14.07 of the South Burlington Land Development Regulations:
(a) The reservation of land may be required on any lot for provision of access
to abutting properties whenever such access is deemed necessary to
reduce curb cuts onto an arterial of collector street, to provide additional
access for emergency or other purposes, or to improve general access and
circulation in the area.
No such access is required.
(b) Electric, telephone and other wire -served utility lines and service
connections shall be underground. Any utility installations remaining
above ground shall be located so as to have a harmonious relation to
neighboring properties and to the site.
Pursuant to Section 15.13(E) of the Land Development Regulations, any new utility
lines, services, and service modifications shall be underground.
(c) All dumpsters and other facilities to handle solid waste, including
compliance with any recycling or other requirements, shall be accessible,
secure and properly screened with opaque fencing to ensure that trash and
debris do not escape the enclosure(s).
No changes are proposed or required at this time.
(d) Landscaping and Screening Requirements
2
FAUSERS\Planning & Zoning\Development Review Board\Findings_Decisions\2011\SP_11_05_550
Dorset_SBSD_ffd.doc
#SP-11-05
The previous approval for the construction of a 1,600 sq. ft. team room, 1,850 sq. ft.
concession stand, and sidewalks included a construction cost of $174,040. The
minimum landscaping requirement was $5,220; the applicant proposed $5,237 in new
landscaping.
With the elimination of the team room and addition of 307 sq. ft of sidewalk, the stated
construction cost for the project is reduced to $86,399. The minimum landscaping
requirement is therefore revised to $2,592. The applicant has proposed $2,604 in new
landscaping.
Lighting
No changes in lighting are proposed.
Water Lines
No changes in water lines are proposed.
DECISION
Based on the above Findings of Fact, the Administrative Officer herby approves SP-11-
05 to amend a previously approved plan for an educational facility complex consisting of
a high school and middle school. The amendment consists of: 1) eliminating a previously
approved but not constructed 1,600 sq. ft. team room building and 2) altering sidewalks
and landscaping, 550 Dorset Street.
1. All previous approvals and stipulations which are not superseded by this approval
shall remain in effect.
2. This project shall be completed as shown on the plans submitted by the applicant
and on file in the South Burlington Department of Planning and Zoning.
3. Pursuant to Section 15.13(E) of the Land Development Regulations, any new utility
lines, services, and service modifications shall be underground.
4. The proposed project shall adhere to standards for erosion control as set forth in
Section 16.03 of the South Burlington Land Development Regulations. In addition,
the grading plan shall meet the standards set forth in Section 16.04 of the South
Burlington Land Development Regulations.
5. The applicant shall obtain a zoning permit within six (6) months pursuant to Section
17.04 of the Land Development Regulations or this approval is null and void.
6. Any change to the site plan shall require approval by the South Burlington
Development Review Board or the Administrative Officer.
Signed on thisJedayof 2011 b9 Y
3
FAUSERS\Planning & Zoning\Development Review Board\Findings_Decisions\2011\SP_11_05_550
Dorset_SBSD_ffd.doc
#SP-11-05 C
r
J. Belair, Administrative Officer
PLEASE NOTE: Pursuant to 24 VSA §4465, an interested person may appeal this
decision by filing a Notice of Appeal with the secretary of the Development Review
Board. This Notice of Appeal must be accompanied with a $113 filing fee and be filed
within 15 days of the date of this decision.
The applicant or permittee retains the obligation to identify, apply for, and obtain
relevant state permits for this project. Call 802.879.5676 to speak with the regional
Permit Specialist.