From:Tom DiPietro
Sent:Monday, August 26, 2024 11:50 AM
To:Marla Keene; Jay Nadeau; Erica Quallen; Marisa Rorabaugh; Paul Conner; Terry Francis;
Casey Follensbee
Subject:Re: MP-24-03 & SD-24-08 850 Hinesburg Road - technical review
Marla,
I'd like to provide the following comments on this application:
The proposed project does not appear to accommodate the City's future ownership of
infrastructure. If this is the applicant's intent, or a future requirement, then we recommend
further discussions to clarify what is necessary.
Any infrastructure in a future City owned ROW, must be constructed in accordance with the South
Burlington Public Works Standards and Specifications. My understanding is that the applicant is
currently proposing a gravel road that would be reconstructed to become a paved road if / when
the road becomes public in the future. The South Burlington Public Works Standards and
Specifications do not include an approved standard for gravel roads. If the DRB were to approve a
gravel road it would need to be reconstructed such that it fully meets the established road
specification for paved roads (including drainage, sub-base, etc) if /when the road becomes public.
This would be highly disruptive to residents then living on the street. DPW would also need to
review the proposed gravel road specification closer to make sure that it could support emergency
vehicles. Under no circumstances will the City accept responsibility for a gravel road in the future.
I do not recommend approval of a gravel road.
The "Neighborhood Street - Narrow" street typology requires a minimum ROW of 40'. The
applicant should consider providing more than the minimum required ROW.
It is unclear if proposed infrastructure including driveway culverts, ditches, water lines, and sewer
pipes are within the proposed 40' wide road ROW. A future submission needs to show this
information on a single sheet. Any infrastructure proposed for future city ownership must be
within the ROW and have sufficient space on either side of the infrastructure to repair / replace /
maintain it in the future. This typically means 10' on either side pipes. Sections of pipe outside the
ROW will require sufficient easements.
Sidewalk location must be shown and included in the ROW.
The applicant will need to obtain an appropriate wastewater allocation to accommodate the
project.
The applicant will need to obtain an appropriate drinking water allocation to accommodate the
project.
The "Neighborhood Street - Narrow" street typology does not accommodate on-street parking.
Applicant will need to provide signage to this effect.
The application should review the City's stormwater ordinance to ensure that policies related to
the future acceptance of stormwater infrastructure are clear.
Thank you for the opportunity to comment.
2
-Tom
From: Marla Keene <mkeene@southburlingtonvt.gov>
Sent: Thursday, August 22, 2024 2:09 PM
To: Tom DiPietro <tdipietro@southburlingtonvt.gov>; Jay Nadeau <jay.nadeau@champlainwater.org>; Erica Quallen
<equallen@southburlingtonvt.gov>; Marisa Rorabaugh <MRorabaugh@southburlingtonvt.gov>; Paul Conner
<pconner@southburlingtonvt.gov>; Terry Francis <tfrancis@southburlingtonvt.gov>; Casey Follensbee
<cfollensbee@southburlingtonvt.gov>
Subject: RE: MP-24-03 & SD-24-08 850 Hinesburg Road - technical review
Hi Everyone,
Thanks for providing your comments. Their hearing got delayed due to an error in process, so I provided them their
master plan comments in advance, and yesterday afternoon they provided updated plans and a response letter
(response saved here: Keene - Prel & Masterl Cover Letter 8-21-24.pdf ). This was all in the context of the Master
Plan, but some of the updated plans are also to the preliminary plat plans for phase 1 (in the preliminary plat
folder). Can you please take a look by Monday and provide updated comments? The updated plans have been
integrated into the folders below. Hopefully it’ll be quick since you’ve already looked at it, and their cover memo is
pretty well organized. Let me know if you have questions.
Sincerely,
Marla Keene, PE
Development Review Planner
City of South Burlington
(802) 846-4106
From: Marla Keene
Sent: Monday, July 1, 2024 2:23 PM
To: Tom DiPietro <tdipietro@southburlingtonvt.gov>; Jay Nadeau <jay.nadeau@champlainwater.org>; Erica Quallen
<equallen@southburlingtonvt.gov>; Marisa Rorabaugh <MRorabaugh@southburlingtonvt.gov>; Paul Conner
<pconner@southburlingtonvt.gov>; Terry Francis <tfrancis@southburlingtonvt.gov>; Casey Follensbee
<cfollensbee@southburlingtonvt.gov>
Subject: MP-24-03 & SD-24-08 850 Hinesburg Road - technical review
Hi folks,
The Wrights have submitted a master plan application and a preliminary plat application for phase 1 to subdivide
their lots and develop additional homes on the new lots. The subdivision involves creation of a new lot
surrounding the existing non-conforming commercial parking facility and development of a new home on that lot,
which is a strange enough thing to do that I’m worried it’ll cause issues. The Board will review this application on
July 16. Please provide comments by Monday July 8.
Master Plan Project description:
Master plan application #MP-24-03 of WGM Associates to subdivide an existing approximately 10.0 acre lot
developed with three homes and an existing non-conforming commercial or private parking facility into ten
single family home lots ranging from 0.26 acres to 2.05 acres, one single family home lot with an existing
non-conforming commercial or private parking facility on 1.52 acres, and one 1.0 acre civic space lot, 850
Hinesburg Road.
Master Plan Folder: MP-24-03_850 Hinesburg_WGM_2024-07-16
Preliminary Plat project description:
Preliminary plat application #SD-24-08 of WGM Associates for phase one of a concurrent master plan for a
development consisting of eleven single family homes and an existing non-conforming commercial or
3
private parking facility. The phase consists of the creation of seven lots, three containing existing single
family homes, two to contain new homes, one to contain an existing non-conforming commercial or
private parking facility and new home, and one civic space lot, 850 Hinesburg Road.
Preliminary Plat Folder: SD-24-08_850 Hinesburg_WGM_PP_2024-07-16
Thanks,
Marla Keene, PE
Development Review Planner
City of South Burlington
180 Market Street
South Burlington, VT 05403
(802) 846-4106
www.southburlingtonvt.gov
Notice - Under Vermont’s Public Records Act, all e-mail, e-mail attachments as well as paper copies of documents received or prepared for use in matters
concerning City business, concerning a City official or staff, or containing information relating to City business are likely to be regarded as public records which
may be inspected by any person upon request, unless otherwise made confidential by law. If you have received this message in error, please notify us immediately by
return email. Thank you for your cooperation.