HomeMy WebLinkAboutPermit Wastewater Allocation Supplemental Info (8)
CITY OF SOUTH BURLINGTON
APPLICATION for WASTEWATER ALLOCATION
*Items marked with an asterisk must be filled in by ALL applicants
*APPLICANT INFORMATION
Applicant: ______________________________________________
Contact Person: ________________________________________________
Mailing Address: _______________________________________________
_______________________________________________
Telephone & Fax for Contact Person: __________________________________
Property Owner Name (if not applicant): _______________________________
Property Owner Mailing Address: ____________________________________
____________________________________
*Physical Location of Project: ________________________________
__________________ ______________________
*Signature of Applicant *Signature of Property Owner
(Both applicant and property owner MUST sign the application!)
*Project Information
If the project is a single-family home, please check one: ____New ____Existing
If not a single-family home, project name: __________________________
*Application or Permit Numbers: (from Planning & Zoning office)
#____-____-____
#____-____-____
#____-____-____
Engineer’s Information for flows over 1,000 gpd
Name of Engineer: ____________________________________________
Firm: _____________________________________________________
Mailing Address: _____________________________________________
Phone & Fax: ________________________________________________
PE License #: ________________________________________________
FOR INTERNAL USE ONLY
WWA Permit #___-____
*Flow Calculations
(You may substitute an engineer’s calculation or letter for the information requested
below)
For residential projects, list number of bedrooms and units requested:
Number of
Bedrooms
Number of Units
X
Gallons per day
per unit =
Total Flows
1 140
2 or more 210
TOTAL
Notes: ___________________________________________________
________________________________________________________
For commercial and industrial projects, list existing and proposed tenants, uses and
flows:
Tenant/ Type of use Number of Flows per Other Total
Business seats, SF, etc X unit Adjustments Flow
TOTAL
*Total development wastewater flow requested: ________gallons per
day
Flow characteristics (for commercial and industrial projects)
Volume:
____________________________________________________________
__________________________________________________
Flow rate:
____________________________________________________________
__________________________________________________
Strength:
____________________________________________________________
__________________________________________________
Please do not write below this line
Application & Recording Fee received: _____________ ________
Name Date
Receiving Plant: ______Airport Pkwy _____Bartlett Bay
City Center District: ____Yes _____No
Approved by Water Pollution Control Department (Commercial and Industrial
Projects)
______________________ _____________
Director of Water Pollution Control Date
Preliminary allocation issued: (payment of fee is not required)
_______________________ _____________
Director of Planning and Zoning Date
Final allocation issued: (payment of fee is required, either in full or pro-rated for
projects with multiple zoning permits involved)
_______________________ _____________
Director of Planning and Zoning Date
Final allocation expires _________________with permit #____-____-____
(Date)
Zoning permit issued___________________with permit#____-____-____
(Date)
Associated WW connection permit (if applicable) #____-____-____
For extensions of Final Allocation Only
EXTENSION GRANTED ____________to______________
(Date) (Date of Expiration)
50% EXTENSION FEE PAID _________ $___________
(Date) (Amount)
Engineers Scientists Planners Designers
40 IDX Drive, Building 100 Suite 200, South Burlington, VT 05403
P 802.497.6100 www.vhb.com
December 1, 2021
Ref: 57913.01
Justin Rabidoux
Public Works Director/City Engineer
City of South Burlington
104 Landfill Rd.
South Burlington, VT 05403
Re: Holiday Inn Redevelopment
1068 Williston Road, South Burlington
Water Design Flow Calculations
Dear Justin,
On behalf of the landowner, Champlain School Apartments Partnership, VHB is writing to request an allocation in
water demand of 24,235 GPD for the Hampton Inn building. The previously approved water demand for the
Hampton Inn building was 17,122 GPD issued on January 17,2019. This new amount reflects an increase in demand
of 7,113 GPD.
South Burlington, VT 05403
Ref: 57913.01
December 1, 2021
Page 2
Wastewater Demand
Table 1 Proposed Wastewater Design Flow Calculations* Hampton Inn
Use Quantity Unit GPD/Unit Wastewater Design Flow (GPD)
Assembly Area; Banquet Hall; Conference Room with food service
-For Each Use 249 Seat 14 3,486
Hotels
-For Each Use 310 Sleeping Space 50 15.500
-Meals served only to
guests
310 Meal per sleeping
space
5 1,550
-On premise laundry 1 Machine 450 450
Office, Factory, Welcome
Center and Place of
Employment
-Without showers 15 Employee Per Shift 15 225
Restaurant service a max.
of 2 meals per day
12 Seat licensed by
the Department of
Health
27 3,024
Total 24,235
*Based on the State Environmental Protection Rules, Chapter 1, Subchapter 8, Table 8-3
Please let me know if you have any questions or need additional information.
Sincerely,
VHB
Stephanie Wyman, PE
Civil Engineer
cc: Peter Smiar, PE (Director of Land Development, VHB)
Deb Sherman (Larkin Realty)