HomeMy WebLinkAboutSP-24-002 - Supplemental - 0154 da Vinci Drive (3)
Stantec Consulting Services Inc. 193 Tilley Drive, Suite 101 South Burlington VT 05403-4440
November 10, 2023
Ms. Marla Keene
Development Review Planner
City of South Burlington
180 Market Street
South Burlington, VT 05403
Reference: Beta Production Facility (BPF) – SD-21-28
Site Plan and Zoning Permit Application for Tree Removal Mitigation
Supporting Documentation – Record Drawings for Permit
Ms. Keene,
The removal of trees noted during your Certificate of Occupancy (CO) inspection associated with SD-21-28
for the BETA Assembly facility, required mitigation to be addressed through a concurrent site plan and
zoning permit application. In total three trees were removed during construction, one by the utility company
to accommodate overhead utility installations and two by the project. To mitigate the tree removal, the
applicant has proposed a solution that thoughtfully positions new trees at the entrance of the site and in the
vicinity of the removed trees. The trees were replaced on a caliper, inch-by-inch basis.
Total Caliper of three (3) trees removed: 80”
Total Caliper of eighteen (18) replacement trees: 81”-84”
The applicant has provided concurrent site plan and zoning permit applications with requested supporting
documentation, including a site plan depicting the new tree locations and a revised tree protection plan for
staff consideration.
As always, should you have any questions, please do not hesitate to give me a call or send me an email.
Best regards,
STANTEC CONSULTING SERVICES INC.
Christopher Gendron PE Senior Associate, Community Development Phone: (802) 324-0920 christopher.gendron@stantec.com
Cc: Art Klugo, Beta Technologies (aklugo@beta.team)