HomeMy WebLinkAboutSP-23-038 - Decision - 0034 Patchen Road #SP-23-038
- 1 –
CITY OF SOUTH BURLINGTON
DEPARTMENT OF PLANNING AND ZONING
ALEXIA OSTROUT – 34 PATCHEN ROAD
SITE PLAN APPLICATION #SP-23-038
FINDINGS OF FACT AND DECISION
Alexia Ostrout, hereinafter referred to as the applicant, is seeking approval to amend a
previously approved plan for a 2,993 sf medical office building. The amendment consists of
constructing a carport in the rear yard, 34 Patchen Road.
Based on the plans and materials contained in the document file for this application, the
Administrative Officer finds, concludes, and decides the following:
FINDINGS OF FACT
1. Alexia Ostrout is seeking approval to amend a previously approved plan for a 2,993 sf
medical office building. The amendment consists of constructing a carport in the rear yard,
34 Patchen Road.
2. The owner of record of the subject property is Brilliant Properties South Burlington, LLC.
3. The subject property is located in Transect Zone 4 of the From-Based Code Zoning District,
Zone 3 of the Traffic Overlay District, and the Transit Overlay District.
4. The application was received on September 12, 2023.
5. The applicant submitted two plan sheets. The first sheet, numbered PV-01, is titled “Site
Plan”, is undated, and was prepared by Suncommon. The second sheet, numbered T-1.1, is
titled “Bents 1, 2, & 3”, and was prepared by NEW Energy Works on 3/18/2022. The
applicant also submitted an untitled and undated image identifying the approximate
location of the proposed bike racks and the concrete slab to which the racks will be affixed.
ZONING DISTRICT & DIMENSIONAL REQUIREMENTS
Setbacks, Coverages & Lot Dimensions
This property is zoned FBC-T4 and is subject to the applicable Building Envelope Standards. The
proposed amendment to this site involves the installation of an accessory structure to the rear
of the principal structure. This amendment will not impact this property’s compliance with the
Building Envelope Standards and, because it does not constitute an alteration of 35% or more of
the existing primary façade and does not include the relocation, replacement, or removal of
more than 50% of load bearing walls or pillars, this project will not necessitate any part of the
principal structure to be brought into greater compliance with the Building Envelope Standards.
Article 8.03.B(3)(c) exempts accessory structures from the Form-Based Code building placement
regulations.
#SP-23-038
- 2 –
SITE PLAN REVIEW STANDARDS
Only the standards below are affected by this application. All other standards will continue to be
met.
13.03 Bicycle Parking
As per Table 13-3, this use has a short-term bicycle parking requirement of one space
per 5,000 sf GFA and a minimum requirement of four (4) spaces. The property currently
has one ‘schoolyard’ bike rack located in the grass to the north of the principal
structure. Because this rack is not of an approved type and is not anchored in a hard,
stabilized surface, it cannot count towards the applicant’s short-term bike parking
requirement. The applicant is proposing to pour a concrete slab of no smaller than 78”
by 80” to the south of the principal structure and the east of the parking area, in
proximity to the principal structure’s primary entrance which faces the parking area. The
slab will contain two ‘inverted U’ bike racks, providing four short-term bike parking
spaces on a hard, stabilized surface of the appropriate size in a location that is accessible
to a primary entrance and protected from motor vehicles. The Administrative Officer
finds this criterion met.
13.04 Snow Storage
Per Section 13.04(B)(7), “snow storage areas must be specified and located in an area that
minimizes the potential for erosion and contaminated runoff into any adjacent or nearby
surface water.” The snow storage areas are indicated on the site plan; the Administrative
Officer finds this criterion met.
13.07 Exterior Lighting
Per Section 13.07.A, exterior lighting “shall have such shielding as will direct the light
downward and will prevent the source of light from being visible from any adjacent
residential property or street.” There are no lighting impacts proposed as part of this
application.
OTHER STANDARDS
3.10 Accessory Structures and Uses
The proposed accessory structure will not exceed 15 feet in height and will not be located
closer than 5 feet from either the side or rear property lines. The Administrative Officer
finds these criteria met.
14.07 Disposal of Wastes
Per Section 14.07.I, dumpsters “shall be accessible, secure and properly screened with
opaque fencing to ensure that trash and debris do not escape the enclosure(s)”. The
applicant is proposing to enclose the existing dumpster with an opaque fence on three
sides and an opaque gate on the fourth side. The Administrative Officer finds this criterion
met.
Vehicle Trip Generation
This property was approved in #SP-06-34 as 2,993 sf of medical office use, which was
found to generate 11.13 PM peak hour VTEs. The applicant has not proposed to change
#SP-23-038
- 3 –
the use of the property in a way that impacts trip generation. The proposed trip
generation will not exceed the previously approved trip generation and therefore the
proposed change of use does not generate any new traffic impacts.
Water & Wastewater
The property previously received approval for a wastewater generation of 210 gallons per
day. The proposed configuration of uses within the building was estimated by the Director
of the Department of Public Works to generate 301 gallons of wastewater per day. As
such, the applicant applied and paid for an increase in their wastewater allocation of 91
gallons per day. The Director of the Department of Public Works issued final approval for
this application, #WW-23-154, on 9/13/2023. As a result, the wastewater allocation on file
for this property is adequate to handle the estimated wastewater generation of the
proposed configuration of uses.
DECISION
Based on the above Findings of Fact, the Administrative Officer herby approves site plan
application #SP-23-038 of Alexia Ostrout, subject to the following conditions:
1. All previous approvals and stipulations which are not superseded by this approval shall
remain in effect.
2. This project must be completed as shown on the plan and shall be on file in the South
Burlington Department of Planning and Zoning.
3. The Administrative Officer concurrently issues Zoning Permit #ZP-23-347.
4. Any new exterior lighting must be installed or shielded in such a manner as to conceal
light sources and reflector surfaces from view beyond the perimeter of the area to be
illuminated.
5. The applicant must obtain a Certificate of Occupancy from the Administrative Officer
prior to occupancy of the items described in this application.
6. Any change to the site plan will require approval by the South Burlington Development
Review Board or the Administrative Officer.
Signed on this 15th day of September, 2023 by
_____________________________________
Marty Gillies, Administrative Officer
#SP-23-038
- 4 –
PLEASE NOTE: Pursuant to 24 VSA §4465, an interested person may appeal this decision by filing
a Notice of Appeal with the secretary of the Development Review Board. This Notice of Appeal
must be accompanied with a $233 filing fee and be filed within 15 days of the date of this
decision.
The applicant or permittee retains the obligation to identify, apply for, and obtain relevant
state permits for this project. Call 802.477.2241 to speak with the regional Permit Specialist.