From:Marla Keene
Sent:Monday, June 5, 2023 8:19 AM
To:Betsy Brown
Subject:FW: Long Drive - Partial Bond Release
Attachments:Long Dr_SD-18-27_Reduction_2023-06-02_executed.pdf
Do you want me to do anything with this email to demonstrate that we sent them the leƩer? (see previous message for
context)
Marla Keene, PE
Development Review Planner
City of South Burlington
(802) 846-4106
From: Tom DiPietro <tdipietro@southburlingtonvt.gov>
Sent: Friday, June 2, 2023 3:21 PM
To: Kemener Whalen <kem@blackrockus.com>
Cc: Marla Keene <mkeene@southburlingtonvt.gov>
Subject: Long Drive - Partial Bond Release
Kemener,
Please see aƩached leƩer related to a parƟal release of bond for Long Drive. The remaining bond amount is now
$129,200.58. Please let me know if you have any quesƟons.
Thanks,
Tom
Thomas J. DiPietro Jr.
Director of Public Works
City of South Burlington
104 Landfill Road
South Burlington, VT 05403
Phone: (802) 658-7961 x6101
Email: tdipietro@southburlingtonvt.gov
Web Site: www.southburlingtonvt.gov
180 Market Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101
www.southburlingtonvt.gov
MEMORANDUM
TO: Andrew Bolduc, City Treasurer
FROM: Dalila Hall, Administrative Officer
DATE: December 22, 2021
SUBJECT: Establishment of Escrow for Project # SD-18-27 (Street Construction) – Long Drive
Pursuant to the above-listed approval by the city’s Development Review Board (DRB), the applicant
has established an Escrow Account. The documents have been prepared using legal documents
prepared by the City Attorney.
The amount included in this Escrow Account has been verified and meets the requirements of the
DRB decision.
The amount of the original surety was: $ 511,290.00. This amount was originally established by JAM
Golf, LLC and has been reduced on four occasions over the course of 2020 to reflect work
completed and approved by Dept. of Public Works.
The current surety amount of the surety is: 167,510.81. This is the amount BlackRock is assuming.
The City will continue to use the original surety value of $511,290.00 as the basis for 10% warranty
value until such time as the City Engineer determines the public facilities and improvements to be
complete as outlined in Section 15.A.20 of the draft Land Development Regulation, warned Nov. 10,
2021.
The surety is required to be maintained until project completion.
Please complete and sign the enclosed three-party agreement authorizing the establishment of this
Escrow Account.
180 Market Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101
www.southburlingtonvt.gov
MEMORANDUM
TO: Andrew Bolduc, City Treasurer
FROM: Dalila Hall, Administrative Officer
DATE: December 22, 2021
SUBJECT: Release of JAM Golf, LLC from Escrow for Project # SD-18-27
(Street Construction) – Long Drive
The applicant’s request for the release of the above-listed Escrow agreement has been reviewed for
the following project: Infrastructure, #SD-18-27
The surety is presently: $ 167,591.81
The purpose of this release is that the original owner (JAM Golf, LLC) is selling the project to the
Adam Hergenrother Family. The Adam Hergenrother Family will now continue the obligation to
maintain this amount for the remainder of the three (3) year term from its initial establishment.
Please complete and sign the enclosed form authorizing the financial institution to release the
funds in Escrow.
180 Market Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101
www.southburlingtonvt.gov
MEMORANDUM
TO: Andrew Bolduc, City Treasurer
FROM: Dalila Hall, Administrative Officer
DATE: December 22, 2021
SUBJECT: Release of JAM Golf, LLC from Escrow for Project # SD-18-27
(Street Construction) – Long Drive
The applicant’s request for the release of the above-listed Escrow agreement has been reviewed for
the following project: Infrastructure, #SD-18-27
The surety is presently: $ 167,591.81
The purpose of this release is that the original owner (JAM Golf, LLC) is selling the project to the
Adam Hergenrother Family. The Adam Hergenrother Family will now continue the obligation to
maintain this amount for the remainder of the three (3) year term from its initial establishment.
Please complete and sign the enclosed form authorizing the financial institution to release the
funds in Escrow.
575 Dorset Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101 www.sburl.com
December 23, 2020
Kemener Whalen
Chief Financial Officer
BlackRock Construction
68 Randall Street
So. Burlington, VT 05403
Re: Authorization for Reduction of Infrastructure Escrow for Project #SD-18-27, JAM Golf LLC-Long Dr
Dear Mr. Whalen:
Please be advised that the City of South Burlington hereby authorizes a third reduction in the amount of
the above referenced escrow required for public infrastructure improvements at the JAM Golf, LLC – Long
Drive project.
The escrow was established with Union Bank VT and can now be reduced as shown below.
Work Covered Initial Value Bonded Bond Value to be Released
Public Infrastructure $ 511,290.00 $ 110,705.87
Should you have any questions, please do not hesitate to contact us.
Sincerely,
Thomas Hubbard
City Treasurer
575 Dorset Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101 www.sburl.com
MEMORANDUM
TO: Tom Hubbard, Treasurer
FROM: Dalila Hall, Administrative Officer
DATE: December 23, 2020
SUBJECT: Reduction of Infrastructure Escrow for Project #SD-18-27
The applicant’s request for the reduction of the above-listed has been reviewed for the following
project: JAM Golf LLC – Long Drive #SD-18-27
The original amount of the surety was: $ 511,290.00
Based on our review, the applicant has qualified for a fourth reduction in the amount of the public
infrastructure surety to: $ 110,705.87
After this reduction the amount of the surety will be: $ 167,510.81
Please review and approve the enclosed letter authorizing the financial institution to reduce the
escrow amount to the amount listed therein.
575 Dorset Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101 www.sburl.com
October 27, 2020
Kemener Whalen
Chief Financial Officer
BlackRock Construction
68 Randall Street
So. Burlington, VT 05403
Re: Authorization for Reduction of Infrastructure Escrow for Project #SD-18-27, JAM Golf LLC-Long Dr
Dear Mr. Whalen:
Please be advised that the City of South Burlington hereby authorizes a third reduction in the amount of
the above referenced escrow required for public infrastructure improvements at the JAM Golf, LLC – Long
Drive project.
The escrow was established with Union Bank VT and can now be reduced as shown below.
Work Covered Initial Value Bonded Bond Value to be Released
Public Infrastructure $ 511,290.00 $ 59,958.73
Should you have any questions, please do not hesitate to contact us.
Sincerely,
Thomas Hubbard
City Treasurer
575 Dorset Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101 www.sburl.com
September 9, 2020
Kemener Whalen
Chief Financial Officer
BlackRock Construction
68 Randall Street
So. Burlington, VT 05403
Re: Authorization for Reduction of Infrastructure Escrow for Project #SD-18-27, JAM Golf LLC-Long Dr
Dear Mr. Whalen:
Please be advised that the City of South Burlington hereby authorizes a second reduction in the amount of
the above referenced escrow required for public infrastructure improvements at the JAM Golf, LLC – Long
Drive project.
The escrow was established with Union Bank VT and can now be reduced as shown below.
Work Covered Initial Value Bonded Bond Value to be Released
Public Infrastructure $ 511,290.00 $ 120,541.51
Should you have any questions, please do not hesitate to contact us.
Sincerely,
Thomas Hubbard
City Treasurer
575 Dorset Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101 www.sburl.com
MEMORANDUM
TO: Tom Hubbard, Treasurer
FROM: Dalila Hall, Administrative Officer
DATE: August 25, 2020
SUBJECT: Reduction of Infrastructure Escrow for Project #SD-18-27
The applicant’s request for the reduction of the above-listed has been reviewed for the following
project: JAM Golf LLC – Long Drive #SD-18-27
The original amount of the surety was: $ 511,290.00
Based on our review, the applicant has qualified for a reduction in the amount of the public
infrastructure surety to: $ 52,573.08
After this reduction the amount of the surety will be: $ 458,716.92
Please review and sign the enclosed letter authorizing the financial institution to reduce the escrow
amount to the amount listed therein.
575 Dorset Street South Burlington, VT 05403 tel 802.846.4106 fax 802.846.4101 www.sburl.com
MEMORANDUM
TO: Tom Hubbard, City Treasurer
FROM: Dalila Hall, Administrative Officer
DATE: August 24, 2020
SUBJECT: Establishment of Escrow for Project # SD-18-27 (Street Construction) – Long Drive
Pursuant to the above-listed approval by the city’s Development Review Board (DRB), the applicant
has established an Escrow Account. The documents have been prepared using legal documents
prepared by the City Attorney.
The amount included in this Escrow Account has been verified and meets the requirements of the
DRB decision.
The amount of the surety is: $ 511,290.00.
The surety is required to be maintained until project completion.
Please complete and sign the enclosed three-party agreement authorizing the establishment of this
Escrow Account.