October 26, 2021
Mr. Justin Rabidoux, P.E., Public Works Director
City of South Burlington Public Works Department 104 Landfill Road South Burlington, VT 05403
Re: 469 Lime Kiln Road Request for Additional Wastewater Allocation Dear Mr. Rabidoux: Please find attached a completed Application for Wastewater Allocation for the property located at 469 Lime Kiln Road in South Burlington. This existing property and its two buildings are currently served by municipal sewer with an existing allocation of 81 gallons per day accordingly to existing State permit
#WW-4-1559. The applicant is seeking approval for additional allocation related to the food truck operation on the property. The food truck is used for food preparation, cooking, and dish washing. In addition, the existing building on the property will be used for packaging food for takeout and delivery.
Also attached is a breakdown of the existing and proposed wastewater demand for the property. An additional 90 gallons per day of wastewater allocation is being requested to serve the property. Please confirm applicable allocation fees and we will coordinate with the applicant on the submission of payment. Please do not hesitate to contact me with any questions or if you need additional information.
Respectfully, Jeffrey P. Kershner, P.E.
President Enc. Cc: Paul Koenig
*Flow Calculations
(You may substitute an engineer’s calculation or letter for the information requested
below)
For residential projects, list number of bedrooms and units requested:
Number of
Bedrooms
Number of Units
X
Gallons per day
per unit =
Total Flows
1 140
2 or more 210
TOTAL
Notes: ___________________________________________________
________________________________________________________
For commercial and industrial projects, list existing and proposed tenants, uses and
flows:
Tenant/ Type of use Number of Flows per Other Total
Business seats, SF, etc X unit Adjustments Flow
TOTAL
*Total development wastewater flow requested: ________gallons per
day
Flow characteristics (for commercial and industrial projects)
Volume:
____________________________________________________________
__________________________________________________
Flow rate:
____________________________________________________________
__________________________________________________
Strength:
____________________________________________________________
__________________________________________________
See Attached.
90
90 gallons per day
gallons per day
domestic
Please do not write below this line
Application & Recording Fee received: _____________ ________
Name Date
Receiving Plant: ______Airport Pkwy _____Bartlett Bay
City Center District: ____Yes _____No
Approved by Water Pollution Control Department (Commercial and Industrial
Projects)
______________________ _____________
Director of Water Pollution Control Date
Preliminary allocation issued: (payment of fee is not required)
_______________________ _____________
Director of Planning and Zoning Date
Final allocation issued: (payment of fee is required, either in full or pro-rated for
projects with multiple zoning permits involved)
_______________________ _____________
Director of Planning and Zoning Date
Final allocation expires _________________with permit #____-____-____
(Date)
Zoning permit issued___________________with permit#____-____-____
(Date)
Associated WW connection permit (if applicable) #____-____-____
For extensions of Final Allocation Only
EXTENSION GRANTED ____________to______________
(Date) (Date of Expiration)
50% EXTENSION FEE PAID _________ $___________
(Date) (Amount)
469 Lime Kiln Road
Estimated Design Flows
Existing Koenig Cedar office building office 3 emp x 15 gpd/emp =45 gpd
Existing building (catering)takeout/delivery 2 emp x 13 gpd/emp =26 gpd
takeout/delivery 1 unit x 100 gpd/each =100 gpd
Total =171 gpd
Total flow all uses =171 gpd
previously approved/allocated =81 gpd
Total New Allocation Request =90 gpd