HomeMy WebLinkAboutSD-21-19 - Supplemental - 0600 Spear Street (18)Transmittal
767 Centerville Road, East Wallingford, VT 05472
Page 1 of 4
PROJECT:Von Turkovich-600 Spear St.-S.
Burlington
19-268
DATE:5/24/2021
SUBJECT:600 Spear Street Preliminary Plat
Plan Set
TRANSMITTAL ID:00004
PURPOSE:For your review and comment VIA:Info Exchange
FROM
NAME COMPANY EMAIL PHONE
Lucy Thayer
767 Centerville Road
East Wallingford, VT
05472
TCE Lucy.Thayer@tcevt.com 802-879-
6331,,108
TO
NAME COMPANY EMAIL PHONE
mkeene@sburl.com mkeene@sburl.com
pconner@sburl.com pconner@sburl.com
REMARKS:Hi Marla,
Please use the link to download the 600 Spear Street Preliminary Plan set that
includes the outstanding items you mentioned, also noted below.
Application Requirement Notes TCE Notes
Plans provided as individual
sheets and named to
include sheet number and
latest revision date must be
submitted.
File names do not
include dates
Date of plans is
provided in the
file names
Boundaries and area of
existing subject property(ies),
proposed property lines,
continues properties,
boundaries of all zoning
districts, transects, and
overlay districts, and all
designations on the City's
Official Map, and lots within
the proposed subdivision
numbered.
Interstate highway
overlay district not
shown
Interstate
highway district is
shown in the
Location Map
A written plan to preserve
and protect significant
It would be OK to
show this on the EPSC
This is included in
the EPSC plan
Transmittal
DATE:5/24/2021
TRANSMITTAL ID:00004
Page 2 of 4
existing vegetation during
and after construction. Such
plan will be of sufficient
detail that the City of South
Burlington will be able to
inspect the site during
construction to ensure that
existing vegetation is
protected as per the plan.
plan but the EPSC plan
doesn’t cover the
whole site, and there
are existing trees to be
retained outside the
area of the EPSC
plan. EPSC details
omitted so tree
protection method is
unknown.
(C2-01, B and C5-
01); a tree
protection detail
is included in LA2-
01
Plans showing the location,
size and invert elevations of
existing and planned
sanitary sewers, storm water
drains, and fire hydrants and
location and size of water,
gas, electricity and any
other utilities or structures.
Electric and gas are
not shown
These are shown
on the plans, see
C3-01
Location and design of all
utility distribution facilities
This refers to things like
transformers and
electric cabinets and
are not shown
These are shown
on the plans, see
C3-01 Utility Plan
Overview
Preliminary designs of any
bridges or culverts which
may be required.
At this preliminary plat
stage, this can be
covered with detail
sheets for how culverts
will be constructed
See the included
detail sheets
Let us know if you need anything else.
Thanks,
Lucy
tcevt.com
Lucy Thayer, PLA
Landscape Architect
e. Lucy.Thayer@tcevt.com
p. 802.879.6331 x108 | c. 802.236.3932
478 Blair Park Road, Williston, VT 05495
42 Mapleville Depot, St. Albans, VT 05478
Transmittal
DATE:5/24/2021
TRANSMITTAL ID:00004
Page 3 of 4
DESCRIPTION OF CONTENTS
QTY DATED TITLE NOTES
1 5/24/2021 C0-00 Cover_2021 0514.pdf
1 5/24/2021 C1-00 Legend & Notes_2021 0514.pdf
1 5/24/2021 C1-01 Existing Conditions_2021 0514.pdf
1 5/24/2021 C2-00 Overall Site Plan_2021 0514.pdf
1 5/24/2021 C2-01 Entrance Plans_2021 0514.pdf
1 5/24/2021 C2-02 Layout & Materials Plan_2021 0514.pdf
1 5/24/2021 C2-03 Grading Plan_2021 0514.pdf
1 5/24/2021 C3-01 Utility Plan Overview_2021 0514.pdf
1 5/24/2021 C3-02 Wastewater and Water Utility Plan_2021
0514.pdf
1 5/24/2021 C3-03 Stormwater Utility Plan_2021 0514.pdf
1 5/24/2021 C3-04 Utility Crossing Plan_2021 0514.pdf
1 5/24/2021 C4-01 Pre DA Plan_2021 0514.pdf
1 5/24/2021 C4-02 Post DA Plan_2021 0514.pdf
1 5/24/2021 C5-01 Overall EPSC Plan_2021 0514.pdf
1 5/24/2021 C6-01 Plan and Profile_2021 0514.pdf
1 5/24/2021 C6-02 Plan and Profile_2021 0514.pdf
1 5/24/2021 C8-401 Stormwater Details_2021 0514.pdf
1 5/24/2021 C8-402 Stormwater Details_2021 0514.pdf
1 5/24/2021 C8-501 Erosion Details_2021 0514.pdf
1 5/24/2021 C10-01 Emergency Vehicle Diagram_2021 0514.pdf
1 5/24/2021 LA1-01 Landscape Plan_2021 0514.pdf
1 5/24/2021 LA1-02 Landscape Plan_2021 0514.pdf
1 5/24/2021 LA2-01 Landscape Details_2021 0514.pdf
1 5/24/2021 LI1-01 Lighting Plan_2021 0514.pdf
1 5/20/2021 Location Map_2021 0520.pdf
1 8/14/2020 Natural Resources Map_2020 0814.pdf
1 5/24/2021 S1-02 PUD Plat_2021 0514.pdf
1 5/24/2021 600 Spear PP_Transmittal_2021 0524.pdf
1 5/11/2021 A1 First Floor Plan_2021 0221.pdf
1 5/11/2021 A2 Second Floor Plan_2021 0221.pdf
1 5/11/2021 A3 Elevations_2021 0221.pdf
1 5/11/2021 A4 Elevations_2021 0221.pdf
Transmittal
DATE:5/24/2021
TRANSMITTAL ID:00004
Page 4 of 4
COPIES:
Frank Von Turkovich (Von Turkovich, Frank)
Abby Dery (TCE)