HomeMy WebLinkAboutAgenda - Recreation and Parks Committee - 11/09/2020RECREATION AND PARKS COMMITTEE
Monday November 9, 2020
5 PM-6:30 PM
VIRTUAL MEETING:
Please join my meeting from your computer, tablet or smartphone.
https://global.gotomeeting.com/join/
You can also dial in using your phone.
Access Code:
(5:00)
(5:10)
(5:20)
(5:30)
(5:50)
(6:00)
(6:10)
(6:20)
(6:30)
AGENDA
Call meeting to order: Katie
Changes or additions to the agenda
Comments from the public not related to the agenda
Approval of minutes from October 26, 2020
Committee Reorganization
Review Final CIP- Sub Committee Comments
Review General Fund Budget Time Line and Committee Involvement
Brief on Joint Committee Development Review of O’Brien Project Nov
30 Review previous joint committee: Underwood Pathway and Dog
Recreation
Annual NRPA Matrix time line
Review Director’s Report- Q&A
Adjourn
RECREATION AND PARKS COMMITTEE
Monday October 26, 2020
5 PM-6:30 PM
Meeting Minutes
Present: Mike Simoneau, Jennifer Kochman, Lauren Wedam, Katie Langrock, William Sudbay,
Christy Pilsucki, Bill Barber
Staff: Holly Rees
Absent: Jon Pence, Caroline Henne
Guests: None
Meeting called to order at 5:03pm by Katie Langrock.
Changes or additions to the agenda
Jennifer said we have not had an organization meeting. The committee usually has one in July
but it was overlooked through pandemic. Holly does not think it needs to be warned so could
do it tonight or at the next meeting. Decision made to do it at the next meeting.
Comments from the public not related to the agenda
None
Approval of minutes from September 28, 2020 meeting
Jennifer moves to approve, Mike seconded it. All approved.
Review Senior Center Fabric/Sample Board and Layout - Holly
Holly reviewed fabric/sample board and layout for Senior Center. Holly said the designer
listened to all the desired amenities and, as the initial cost was higher than budgeted, the
designer had to make alterations but did not compromise on vision, fit and finish.
Jennifer likes the design, thinks throw pillows would be nice. Holly said there is no plan for
accents and that may be left to R&P so input will be appreciated.
Holly said construction is in progress. Holly said committee members can go on site and look in
the windows of the building if they respect construction zones. Holly hopes that the committee
will be able to tour it more formally once the site is no longer a danger zone. R&P Committee is
interested in doing this.
Holly said they added a senior center icon to city website, but it is a work in progress. Currently,
it has the history of Market Street and a visual layout of senior center. They plan to have an
FAQ, updates, contact information as well as meal and activity calendars in the future.
Dog Recreation Task Force - Holly
Holly said she wanted to give some background on this before the meeting tomorrow (10/27).
She said that late last winter/early spring they reviewed the management plan of Red Rocks
and realized that there was a larger conversation about dog culture in the community. Holly
said she receives weekly calls from residents about negative experiences with dogs and dog
owners. Ashely Parker has helped to outline steps to create a positive dog culture in the City
which includes dog recreation. They plan to look at ordinances, create an education campaign.
The staff’s question is whether the Dog Park Committee can take on this work as it might be
beyond the current scope of their committee. Dog Park Committee would like to broaden their
scope beyond creation of parks. They would like input from committees about where this work
should happen. Jennifer said she thinks the Planning Commission might be included as well.
Wheeler Dog Park update – Mike
Mike said they looked at site plan during last meeting. Mike said it does not look like wetlands
are not too much of an issue. Mike said they have been talking with Common Roots to
establish consistent communication in hopes of avoiding issues in the future. Mike said they
are going to need more parking, but they are not going to address this until site plan is
approved. They will defer to Justin on this issue. Holly said she noticed in the minutes that
construction would start “early 2021,” but she does not know if this means Jan or April/May.
She will try to clarify. Holly said she received a map of the boundaries of the dog park and
Common Roots event areas. Additionally, the Dog Park Committee would like a sentence in the
lease indicating the dog park will be operation daily, dawn to dusk regardless of any other
events happening adjacent. Carol (CR) hoped there would be some flexibility and the dog park
might close if there was a special event happening. Final draft of lease will be developed in the
next week or two and then vetted through City Council.
Auclair Property Trail Development – Holly
Holly reached out to Paul Conner with update but has not heard back yet. Holly said part of the
Auclair arrangement was to provide public access trails but unclear what that will look like right
now. Holly said South Burlington will not own the land so it is uncertain how much Holly should
insert R&P and the public into this process. Paul and Travis walked the land with one of the
farmers and a local trail developer did a 2 hour walk through to get some ideas of potential
trails. Holly said the farmer already has an idea of what they would like to see. Holly is not sure
if this will be more developed trails or miles of a mowed path with fencing around it for
farmers. Holly sees potential issues around accessibility, maintenance and building a trail
network. Main question is who is putting money into this project and how much of a say does
South Burlington have in it? Holly is keeping tabs on the project but may not have control over
the process. Holly said there is interest on the Williston and Shelburne sides to connect the
trails.
Mike said it might be beneficial to defer this to the other communities in terms of what makes
sense in creating the trail. If there is interest in connecting these three communities, it may be
good to get some energy there. Mike questioned, if South Burlington has additional money,
would our priority be to use it for Underwood or Auclair?
Trail Mapping Project Update – Holly
Holly said R&P Dept often get calls asking where residents can hike that is not in a park. In
response to this, Travis is going to map out informal hiking trail system in the City. Holly said
this is more complicated that it may seem because some of the trails are through private HOAs
(i.e. Winding Brook) and easements. Right now, Travis is looking at where are the trails, where
are the gaps in connectivity, how to maintain these trails and how to promote them in the city.
Holly said they what to be intentional about marking it as an asset and having a maintenance
plan. There are lots of great trails, but people do not know about them.
CIP review-Holly
Holly said she will send draft CIP to subcommittee members. Holly said it is important to note
that they are prepping for 2022, currently in 2021. Holly moved big chunks of CIP from 2021
and prioritized them in 2022. She said she looked back to 2020 and what did not get done at
the beginning of pandemic. These projects will receive priority as well. Holly said two additional
items that will need to be added is the bathroom renovation and defunct hockey area both at
Veterans Memorial. Holly said we will likely not get an increase in budget, may even get a
decrease. Holly said any input should go directly to Holly and then will schedule either a group
phone call or meeting. Jennifer suggested a 1-2 page summary should go to the Planning
Commission as well as City Council so they know our priorities and CC.
Open space project updates – Jon
Deferred to next meeting as Jon is not present.
Director’s Report Review – Holly
It is long and detailed! Holly said staff want to reflect the hard work they are doing. Katie
suggested Holly highlight in the email which parts are most important, so we draw our
attention to it. Jennifer said she likes it as a historical document and finds it very rich. Jennifer
said she thinks the public should know all the important information in this report. Holly said
she said would love the committee’s support in identifying important information that should
be shared with the public on the website as they work to make the website more robust. Katie
suggested the committee can help identify what is interesting and then develop a
communication plan out of that. Jennifer asked Holly to write a memo to committee asking for
items that are important to share with the public.
Community Outreach/Marketing - Holly
Holly said they are working on improved outreach to the public. Holly said the R&P Department
is great at marketing events, but not ourselves, our parks or creating engagement of the public.
Ongoing assessment of R&P’s voice on Twitter, FB, FPF, etc. Holly said they find that people do
not engage with it, especially if they send the same message out on all platforms. One thought
is a video fireside chat with staff which they post on YouTube channel. Holly said they recognize
this as an area of opportunity and want to be intentional about it. Jennifer Murray and Holly
reached out to the Other Paper to request space for community updates. Holly said they know
the Other Paper cannot offer free marketing, but can we have a weekly column?
Overlook Park project – Lauren
Lauren observed a man removing the caution tape to walk on the stone wall. Lauren engaged
him around replacing the caution tape as it is a safety indication. Lauren said the conversation
shifted to the project itself and other community members joined. Members shared their
displeasure with the project, and it seemed contentious. Lauren did not engage outside of
safety issue with tape. Holly said she has had a similar experience and believes it is related to a
sense of equity and protecting view corridors. Holly said some people do not understand that
the home this project is protecting from light pollution was there before the park and so that
was part of the deal made with this resident to create the park. Again, related to
communication and outreach, Holly said it would be helpful to have a “Did You Know” column
somewhere for public.
Mike moved to adjourn the meeting at 6:17pm, Lauren seconded. All approved.
Respectfully submitted,
Christy Pilsucki
GENERAL FUND
RECREATION AND PARKS
GENERAL FUND
RECREATION AND PARKS OVERVIEW BY EXPENDITURE
RECREATION AND PARKS CIP PROJECTS OVERVIEW:Total Estimated Revenues:
Total Estimated Savings:
Department Contact:Holly Rees
Changes from FY 2019-2028 CIP:
SUMMARY CIP EXPENDITURES (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
145 125 - - - - - - - - 270
15 - - - - - - - - - 15
- - 50 500 250 - - - - - 800
10 - - - - - - - - 10
- 45 - - - - - - - 45
20 - - - 50 - - - - - 70
- - - - - - - - 60 - 60
500 - - - - - - - - 500
- - - 100 - - - - - - 100
- 50 - - - - - - - - 50
- 150 150 150 - - - - - - 450
15 15 15 15 15 - - - - - 75
190 - - 25 - - - - - - 215
60 - - - - - - - - - 60
100 - - - - - - - - 100
70 10 - - - - - - - 80
25 10 - - - - - - - 35
TOTAL ESTIMATED CIP EXPENDITURES:470 1,030 270 790 315 - - - 60 - 2,935
Overlook Park
0
The Recreation & Parks Department is responsible for planning for future active and passive recreational needs for the community,
including the purchase and development of additional land for parks, as well as maintaining, expanding and improving facilities and
equipment.
0
South Village Soccer Field
Irrigation System Upgrades
Jaycee Park Neighborhood Facility
Bleacher Replacement
Jaycee Park Improvements
Szymanski Park Improvements
Farrell Playground Replacement
Red Rocks Facility Replacement
Wheeler House Improvements
Fleet Replacement
Dog Park- Ammenities
Recrowning of Athletic Fields at Vet
Baseball Field Dugout Replacement
Veteran Memorial Park Upgrades
Vet Memorial Basketball Courts
Parks System Master Plan
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:South Village Soccer Field
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 125 125
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:125 - - - - - - - - - 125
Funding Sources:
General Fund -
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt -
Road Improvement Impact Fee -
Recreation Impact Fee 125 - - - - 125
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:125 - - - - - - - - - 125
STATUS: land set aside.
DESCRIPTION: Develop a soccer field in South Village
OPERATING BUDGET IMPACT: none
JUSTIFICATION: Part of the South Village project.
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks | Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Overlook Park
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction -
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:- - - - - - - - - - -
Funding Sources:
General Fund 35 - - - - - - 35
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Bond -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:35 - - - - - - - - - 35
STATUS: Concept
DESCRIPTION: Redo/give a facelift to Overlook Park. Initial paving has been completed. Walk way
improvements, vegetation replantings and viewing cooridors are next priorities
OPERATING BUDGET IMPACT: none
JUSTIFICATION: Park is heavily used but has aged; simply repaving and other maintenance-like items
would not do enough to ensure the Park is as attractive as it should be for the next 20 years
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks | Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Jaycee Park Neighborhood Facility
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal 50 50
Land/ROW/Easement Acquisition -
Construction 500 250 750
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:- - 50 500 250 - - - - - 800
Funding Sources:
General Fund - -
Grant/Donation/Developer Contribution 50 100 150
Current Bond -
Anticipated Debt 400 250 650
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:- - 50 500 250 - - - - - 800
STATUS: land set aside.
DESCRIPTION: When the O'Brien Center was demolished, the community was promised a facility to
replace the function of the previous stucture. Community engagement to determine desired elements
and initial designs will be part of the initial work in FY24 with construction phases to follow in
subsequent years.OPERATING BUDGET IMPACT: none
JUSTIFICATION: Jaycee Park is a high usage park. Needs updating.
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Bleacher Replacement
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction -
Furniture & Equipment 10 10
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:10 - - - - - - - - - 10
Funding Sources:
General Fund 10 - 10
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt - - - - -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:10 - - - - - - - - - 10
STATUS:
DESCRIPTION: There are two damaged bleachers at Veteran’s Memorial that need to come out of
rotation as they pose a safety threat to users. This would allow for those two lower bleachers to be
removed.
OPERATING BUDGET IMPACT: none
JUSTIFICATION: Purchasing of two new portable bleachers to replace antiquated systems at Jaycee and
Upper Farrell will bring us into full alignment at all parks.
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Jaycee Park Improvements
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 45 45
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:- 45 - - - - - - - - 45
Funding Sources:
General Fund -
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Facility Use Fees 45 45
TOTAL FUNDING SOURCES:- 45 - - - - - - - - 45
STATUS:
DESCRIPTION: There is currently not a skinned softball field in our So. Burlington inventory, an element
that many other like sized communities have. A growing interest in both youth and adult softball have
been vocal in their interest to have the Jaycee Park field skinned and reserved only for softball (FY21).
South Burlington Youth Baseball/Softball league has offered to support this work through some
fundraising efforts. While playgrounds are inspected annually by our Parks Foreman (a Certified
Playground Safety Inspector), it is the industry standard to plan for full replacement 30 years post
installation (FY23).
OPERATING BUDGET IMPACT: none
JUSTIFICATION: Ensuring the safety and integrity of playgrounds is essential to our park patrons.
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Szymanski Park Improvements
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 20 20
Furniture & Equipment 50 50
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:20 - - - 50 - - - - - 70
Funding Sources:
General Fund 20 50 70
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:20 - - - 50 - - - - - 70
STATUS:
DESCRIPTION: Resurfacing and painting of tennis courts in FY 21 to include tennis and pickle ball lines
and recap/and paint basketball courts. This would also include instalation of a rubermaid storage
container to store portable pickle ball nets and supplies. While playgrounds are inspected annually by
our Parks Foreman (a Certified Playground Safety Inspector), it is the industry standard to plan for full
replacement 30 years post installation. This will occur in FY2026
OPERATING BUDGET IMPACT: none
JUSTIFICATION: Ensuring the safety and integrity of playgrounds is essential to our park patrons.
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Farrell Playground Replacement
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction -
Furniture & Equipment 60 60
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:- - - - - - - - 60 - 60
Funding Sources:
General Fund - - - - - - - - 60 - 60
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:- - - - - - - - 60 - 60
STATUS:
DESCRIPTION: Ensuring the safety and integrity of playgrounds is essential to our park patrons. While
playgrounds are inspected annually by our Parks Foreman (a Certified Playground Safety Inspector), it is
the industry standard to plan for full replacement 30 years post installation.
OPERATING BUDGET IMPACT: none
JUSTIFICATION:
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Red Rocks Facility Replacement
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 500 500
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:-500 - - - - - - - - 500
Funding Sources:
General Fund 500 500
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt - - - -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:-500 - - - - - - - - 500
STATUS:
DESCRIPTION: Renovation and/or replacement costs for the Red Rocks Bathhouse did not make top
priority with the Open Space Funds, yet remains an essential need. We hear comments weekly in the
summer months from patrons about the limited functionality of the facility, as well as the ongoing
frustration that maintaining the plumbing of the facility is to the Parks Foreman. Each year we have
more limited ammenities and are only to provide functionality to about 1/4 of the original design
elements of the facility. Currently, the Deputy of Public Works is looking into options for a prefabricated
facility to replace the existing structure.
OPERATING BUDGET IMPACT: none
JUSTIFICATION:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Wheeler House Improvements
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 100 100
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:- - - 100 - - - - - - 100
Funding Sources:
General Fund 100 100
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt - - -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:- - - 100 - - - - - - 100
STATUS:
DESCRIPTION: The Wheeler House boiler/heating system is old and antiquated. Well-functioning,
reliable and efficient system replacement is highly desirable (FY25). With two current tenants in the
building, it is essential that we plan for the upgrades and not wait to be reactive, as the costs are
substantial. OPERATING BUDGET IMPACT: none
JUSTIFICATION:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Irrigation System Upgrades
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction -
Furniture & Equipment 50 50
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:- 50 - - - - - - - - 50
Funding Sources:
General Fund 50 50
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt - - -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:- 50 - - - - - - - - 50
STATUS:
DESCRIPTION: As the fields at Veteran's Memorial are re-crowned there will be needed changes to the
irrigation system and along with it, an overalhaul of the original system which currently has several
break/fix issues annually.
OPERATING BUDGET IMPACT: none
JUSTIFICATION:
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Recrowning of Athletic Fields @ Vet
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 150 150 150 450
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:- 150 150 150 - - - - - - 450
Funding Sources:
General Fund 150 150 150 450
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt - -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:- 150 150 150 - - - - - - 450
STATUS:
DESCRIPTION: The athletic fields at Veteran’s Memorial are over two decades old and have not been re-
crowned since their installation. It is best practice to do this every 10-15 years with normal use. Our
fields have excessive use and are in need of rehabilitation. This would need to be done in stages, as a
field needs to be taken off line for a whole year to complete this process.OPERATING BUDGET IMPACT: none
JUSTIFICATION: Re-crowing will allow for water to naturally roll off the field and mitigate pooling, which
leads to field damage, rutting and potential player injury.
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Baseball Field Dugout Replacement
N/A
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 15 15 15 15 60
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:15 15 15 15 - - - - - - 60
Funding Sources:
General Fund -
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt - -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Facility Use Fees 15 15 15 15 60
TOTAL FUNDING SOURCES:15 15 15 15 - - - - - - 60
STATUS:
DESCRIPTION: The dug outs were constructed years ago in conjunction with South Burlington Little
League and through contract with the Burlington Technical School. As these age, they are showing signs
of wear and tear. Though fresh paint has been applied as needed and single repair when required, the
time to replace one set annual has arrived. With park staff time being used for field maintenance and
increased need for specialty gardening at several facilities, it is necessary to contract out of this work.
OPERATING BUDGET IMPACT: none
JUSTIFICATION:
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Veteran Memorial Park Upgrades
N/A
0
DEPARTMENT/STAFF CONTACT:
Holly Rees
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal 25 25
Land/ROW/Easement Acquisition -
Construction 165 165
Furniture & Equipment -
Anticipated Debt Repayment -
TOTAL ESTIMATED COSTS:190 - - - - - - - - - 190
Funding Sources:
General Fund 190 - - 190
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Bond -
Road Improvement Impact Fee -
Recreation Impact Fee -
Trade-In Generated Revenues -
Other: Open Space Fund -
TOTAL FUNDING SOURCES:190 - - - - - - - - - 190
STATUS:
DESCRIPTION: We had hoped that a New Indoor Recreation Center would support new bathroom
facilities for park users. Lacking a firm plan in these uncertain times, the issue of bathroom renovation
and/or replacement is once again upon us ( approx $125K) Additionally, there is a beam on the
bandshell that will need to be replaced which will require roof removal. The parks foreman is doing OPERATING BUDGET IMPACT:
JUSTIFICATION: Ability to provide a suitable facility that supports both continued general park use and
future events.
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: AVE ESTIMATED REVENUES PER YEAR:
Recreation & Parks
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Vet Memorial Basketball Courts
0
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction 60 60
Furniture & Equipment -
Anticipated Debt Repayment
TOTAL ESTIMATED COSTS:60 - - - - - - - - - 60
Funding Sources:
General Fund 60 - - - - - - - - 60
Grant/Donation/Developer Contribution
Current Bond
Anticipated Debt
Road Improvement Impact Fee
Recreation Impact Fee
Trade-In Generated Revenues
Other: Open Space Fund
TOTAL FUNDING SOURCES:60 - - - - - - - - - 60
STATUS:
DESCRIPTION: Complete Recap of basketball courts plus resurfacing and paint
OPERATING BUDGET IMPACT: None
JUSTIFICATION: protection and maintenance of asset and safety of users
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT:AVG ESTIMATED REVENUES PER YEAR:
DEPARTMENT/STAFF CONTACT:
Recreation & Parks |Holly Rees
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:Parks System Master Plan
0
DEPARTMENT/STAFF CONTACT:
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal 100 100
Land/ROW/Easement Acquisition -
Construction -
Furniture & Equipment -
Anticipated Debt Repayment
TOTAL ESTIMATED COSTS:100 - - - - - - - - - 100
Funding Sources:
General Fund 100 - - - - - - - - 100
Grant/Donation/Developer Contribution
Current Bond
Anticipated Debt
Road Improvement Impact Fee
Recreation Impact Fee
Trade-In Generated Revenues
Other: Open Space Fund
TOTAL FUNDING SOURCES:100 - - - - - - - - - 100
STATUS: This is a request directly from the Recration and Parks
Committee and has been a long standing goal of their work planDESCRIPTION: It has long been desired that our parks system take an accounting of our current
assests and plan for additional needs that the gap annalyis showed. In addition, it is essentail that
we prepare for the future, highlighting desired parks, lands and ammenities to provide for our
current and future community.OPERATING BUDGET IMPACT: None
JUSTIFICATION: protection and maintenance of asset and safety of users
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT:AVG ESTIMATED REVENUES PER YEAR:
Recreation & Parks |Holly
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:
0
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction -
Furniture & Equipment 70 10 80
Anticipated Debt Repayment
TAL ESTIMATED COSTS:70 10 - - - - - - - - 80
Funding Sources:
General Fund 70 10 - - - - - - - 80
Grant/Donation/Developer Contribution
Current Bond
Anticipated Debt
Road Improvement Impact Fee
Recreation Impact Fee
Trade-In Generated Revenues
Other: Open Space Fund
L FUNDING SOURCES:70 10 - - - - - - - - 80
DEPARTMENT/STAFF CONTACT:
Recreation & Parks | Holly Rees
Fleet Replacement STATUS: currently we have a truck that is not likely to
pass inspection without major renovation and body
work.
DESCRIPTION: Replacement Cost of Recreation Department Truck and Purchase of
Accessible Van prior to the opening of the Senior Center at Market Street. Also, With an
increase in programs and events, we have to rely on DPW to move large items ( ie the
gator at Red Rocks) to and from facilities. If we had our own trailer to haul larger
equipment and camp needs (ie bikes) that would streamline and ease in facilitiation of our
offerings.
OPERATING BUDGET IMPACT: None
JUSTIFICATION: Vehicles necessary for programs and events
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT: DPW will continue to work with our department to fill this need
from other department inventories coming off line until we can get replacement costs
added in
AVG ESTIMATED REVENUES PER YEAR:
GENERAL FUND - RECREATION AND PARKS
CAPITAL IMPROVEMENT PROGRAM EXPENDITURE
PROJECT:
0
FINANCIALS (in $1,000)FY 22 FY 23 FY 24 FY 25 FY 26 FY 27 FY 28 FY 29 FY 30 FY 31 Total:
Estimated Costs:
Studies, Design, Engineering, Inspection, GC, Legal -
Land/ROW/Easement Acquisition -
Construction -
Furniture & Equipment 25 10 35
Anticipated Debt Repayment
TAL ESTIMATED COSTS:25 10 - - - - - - - - 35
Funding Sources:
General Fund - - - - - - -
Grant/Donation/Developer Contribution -
Current Bond -
Anticipated Debt -
Road Improvement Impact Fee -
Recreation Impact Fee 25 10 35
Trade-In Generated Revenues -
Other: Open Space Fund
L FUNDING SOURCES:25 10 - - - - - - - - 35
DEPARTMENT/STAFF CONTACT:
Recreation & Parks |Holly Rees
Dog Park- Ammenities STATUS:
DESCRIPTION: As the City Council appointed Dog Park Committee begins its work, it will be
necessary for funds to construct additional dog parks/ammenities in the city. Assuming a
modest budget as a placeholder for such development of Wheeler, Phase 2 improvements
to Farrell and potenial design work for additional lands.OPERATING BUDGET IMPACT: None
JUSTIFICATION:To support City Council directed committee work
AVG ESTIMATED SAVINGS PER YEAR:
FINANCIALS COMMENT:AVG ESTIMATED REVENUES PER YEAR:
FY22 BUDGET SCHEDULE
*Denotes regular City Council meeting dates
Sept-Oct Staff liaison discusses FY22 CIP and General Fund/Special Funds
with committees and solicit input & recommendations for
funding
October 19* Council Approval of FY22 General Fund Budget Schedule
Discussion for FY22 General Fund Budget Preparation
Nov 9-12 Dept. Manager meetings w/ City Management for final CIP
Review
Nov 23 First Draft of FY22 Budget due from Dept. Managers to Finance
Dec 1-4 Management review of Draft Budget with Dept. Managers
Dec 8-11 Management final review of FY22 budget with Dept. Heads
Dec 18 Proposed CIP sent to Council
Council receives Draft FY22 GF Budget
Dec. 21* FY22 Proposed Budget Overview presented to City Council
January 4* & 11 Council Mtg.(s) on FY22 Proposed Budget
Public Hearing & Potential Council Amendment of CIP
January 14 Final date (if needed) for City Council budget approval
Council budget sent to Steering Committee (min. 45 days before
vote)
January 20 Steering Committee Meeting (tentative, post in paper 7 days in
advance)
January 21-28 Budget book preparation & printing
Council budget available to voters (min 20 days before Town
Mtg.)
January 29 Post Warnings and Public Hearing Notices (min. 30 days) for
March 1 Pre- Town Mtg. & Public Hearing and March 2 Town
Meeting Vote
Budget booklets available & posted on websites
March 1 Pre-Town Meeting & Public Hearing on City & School District
Budgets
March 2 Vote on budgets and any other warned articles
1
Joint meeting of the Recreation and Parks, Natural Resources and Conservation,
Bicycle and Pedestrian, and Dog Park Committees on Tuesday 10/27/20 at 5:30
pm.
Attending:
Staff: Holly Rees and Ashley Parker
Committee members: David Crawford (Natural Resources & Conservation),
Amanda Holland (Bicycle & Pedestrian), Barb Sirvis (Dog Park), Bob Britt (Bicycle &
Pedestrian), Catherine Frank (Bicycle & Pedestrian), Colin MacIntosh (Natural
Resources & Conservation), Corey Santorello (Natural Resources & Conservation),
Dana Farr (Bicycle & Pedestrian), Drew Shatzer (Natural Resources &
Conservation), Havelah Gagne (Bicycle & Pedestrian), Eric Silverman (Bicycle &
Pedestrian), Katie Langrock (Recreation & Parks), Linda Chiasson (Dog Park), Lisa
Yankowski (Natural Resources & Conservation), Muriel More (Dog Park), Nic
Anderson (Bicycle & Pedestrian), Ray Gonda (Natural Resources & Conservation),
Shawn Goddard (Bicycle & Pedestrian), William Barber (Recreation & Parks), Will
Sudbay (Recreation & Parks), Elizabeth Milizia (Dog Park), Donna Leban (Bicycle &
Pedestrian), Larry Kupferman (Natural Resources & Conservation; Dog Park)
Members of the public: Andrew Chalnick, Sophie Mazowita
1)Presentation/Discussion of the Underwood Project: (Meeting of the
Recreation and Parks, Natural Resource and Conservation, and Bicycle and
Pedestrian Committees)
Ashley shared the current site plan and described several elements of the
shared use portion under discussion tonight. Some areas of concern are
parking, speed on Nowland Farm Rd, access points to Underwood. Striping is
planned to Nowland Farm Rd to designate parking spots on the side of the
road. Trail assessment underway to make good connections between the
woodland and meadow trails
Comments:
Cathy F: comments on the end of the shared use path at the southern end
joining the end of Parkside Drive sidewalk becoming an access point.
2
Nic A: why is the shared use path not following the existing mowed path?
Ashley: the proposed shared use path follows a course that will affect wetland
areas with the least disturbance and still be able to connect to other planned
paths and the viewpoint.
Nic A: have you consider a 12 ft path rather than the current 10 ft wide? And
will it be plowed?
Ashley: yes, all SoBu paved paths are ploughed thus the 10’ wide design.
Nic A also asked about the design and engineering of a crosswalk (location?)
and Ashley will look into that question.
Muriel M asked about an access point from Spear St at the south end of the
property so that her neighborhood could access the park from across the
street.
Ashley points out Class II wetlands in that immediate area and issues with
people crossing the wetlands.
Holly mentioned funds might be available to provide an access point at Spear
and Pheasant Way.
Discussion about crossings between Deerfield and South Village and how
penny for paths might be used for a bike lane, crossings and additional
infrastructure on Spear St.
2) Presentation/Discussion of Dog Recreation Management in South
Burlington Natural Areas: (Meeting of the Recreation and Parks, Natural
Resources and Conservation and Dog Park Committees)
Holly : management plans for Wheeler Homestead and Natural area, Red
Rocks Park include significant concern for public safety and maintenance of
fragile natural systems in place. If dogs are allowed access to these areas, what
should it look like and if restrictions are considered, then how should they be
implemented.
She suggested we look at these questions through three lenses: natural
resources, recreation and dog activities and asked about reactions to how/who
3
should proceed with proposals as described in the materials prepared by staff
for the meeting entitled “Dog Recreation in South Burlington; Strategies for
Natural Resources Protection and Management while Sharing Outdoor Spaces
with Dogs”.
Holly referenced the research that the Dog Park Committee did to select an
area (Wheeler Homestead, northern sloped area) as a site for a new dog park.
Discussion:
Larry K: would rather see a task force comprised from various committees in
order to look thru the “lenses” as Holly referenced.
Linda C: described the process used by the Dog Park committee to reach the
decision to recommend Wheeler Homestead as a site for a dog park.
Muriel M: supports an expanded mission for the Dog Park Committee,
referenced some of the research Dog Park members did about “dog
recreation” and described the work in Boulder CO as a good resource for
future research into best practices. She questioned the pros and cons of a dog
permit and further suggests that any plan should include off leash options and
use the regional partnership as a source.
Elizabeth M agrees that a task force be created to address the issues.
Lisa Y: comments on dog issues at Red Rocks and the number of out of
towners using Red Rocks as a place to walk their dog. She suggests better
monitoring.
Holly says a broader perspective at play now to rework the management plans
with a tiered approach with feasibility of monitoring to better address issues
as well as improve or create educational campaigns.
Ray G: concerned with off leash behavior without a closer look at wildlife and
habitat focus; sees Underwood as part of the wildlife corridor through that
part of town leading south.
Ashley offers that research shows that communities value land according to
usage and that potential future strategies should come from committees
assigned to the tasks.
4
Colin M: traffic at Red Rocks from Burlington and how would a So. Burlington
permit proposal affect that usage?
Holly: been working with her counterpart at Burlington Parks Dept since there
is no dog park facility in the southern section of Burlington. She would like to
see a social agreement about the affects of dog waste as part of dog
permitting (and licensing?)
Elizabeth M: Friends of Dog park group has created a trifold handout and could
do more with feedback from others as to what information should be
included. She sees the role of the Friends group to volunteer and offer
educational materials.
Holly: general sense from the meeting that a task force comprised of members
from the 3 committees be proposed to Council and have the chairs of each
make the presentation. We should vet the idea thru the committees and
consider a time in January for Council action.
Minutes taken by Larry K.