FOUR BOYS, LLC. — 23 SAN REMO DRIVE
SITE PLAN #SP-04-31
FINDINGS OF FACT AND DECISION
Bill Michaud, hereafter referred to as the applicant, is requesting site plan re -
approval to amend a previously approved site plan for a 7200 sq ft building
consisting of 3600 sq ft of medical office and four (4) dwelling units. The
amendment consists of constructing a 4089 sq ft addition which will consist of
2089 sq ft of medical office use and two (2) dwelling units, 23 San Remo Drive.
The Development Review Board held a public meeting on September 21, 2004.
Bill Michaud was present at the meeting.
Based on testimony provided at the above mentioned public meeting and the
plans and supporting materials contained in the docurnent file for this application,
the Development Review Board finds, concludes, and decides the following:
FINDINGS OF FACT
1. The applicant is requesting site plan re -approval to amend a previously
approved site plan for a 7200 sq ft building consisting of 3600 sq ft of
medical office and four (4) dwelling units. The amendment consists of
constructing a 4089 sq ft addition which will consist of 2089 sq ft of
medical office use and two (2) dwelling units, 23 San Remo Drive.
2. The property is located in the Central District 2 (CD2) Zoning District.
3. The owner of record is Four Boys, LLC.
4. The plans consist of a two (2) page set of plans, page one (1) entitled, "23
San Remo Drive Four Boys LLC 23 San Remo Drive South Burlington VT
864-1812", prepared by Groundswell Architects, dated 9/8/04.
5. The applicant received approval for this project on January 28, 2003, but
the approval lapsed. This application is for re -approval of the same
project.
Zoning District & Dimensional Requirements:
The proposed density for the property is an F.A.R. of 0.5. This is the
maximum allowed F.A.R. for the CD2 District. Therefore, the proposed
density complies with the zoning regulations.
2. The proposed building coverage for the lot is 25%. The maximum allowed
building coverage for the CD2 District is 40%. The proposed overall
coverage for the lot is 72%. The maximum allowed overall coverage for
the CD2 District is 90%. The proposal complies with the lot coverage
requirements of the zoning regulations. The DRB notes that the proposed
garden roof will mitigate the proposed lot coverage.
3. Pursuant to Section 14.402(b) of the zoning regulations, allowable building
envelopes along San Remo Drive shall be between 32 ft. from the
centerline of the right-of-way and 80 ft. from the nearest edge of the right-
of-way. The building envelope is greater than 80 ft. from the San Remo
Drive right-of-way, but this is a condition of the existing structure and not
the proposed new structure. The plans indicate that the new structure is at
least 32 ft. from the centerline of the right-of-way on the north and the east
sides.
SITE PLAN REVIEW STANDARDS
Section 14.06 of the South Burlinaton Land Development Reaulations establishes
the followina aeneral review standards for all site plan aaolications:
(a) The site shall be planned to accomplish a desirable transition from
structure to site, from structure to structure, and to provide for
adequate planting, safe pedestrian movement, and adequate parking
areas.
The proposed project has been planned to accomplish a desirable transition from
structure to site, from structure to structure, and to provide for adequate planting,
safe pedestrian movement.
Pursuant to Table 13-2 of the Land Development Regulations, the proposed project
will require 42 parking spaces. The applicant is proposing 23 parking spaces.
Since the medical office and residential units will have different peak -hour parking
demands, the applicant has submitted a shared parking analysis that indicates the
proposed project will require a total of 23 parking spaces.
Pursuant to Section 13.01(G)(5) of the Land Development Regulations, the plans
depict a bicycle rack.
(b) Parking shall be located to the rear or sides of buildings to the greatest
extent practicable.
The parking spaces are located to the side and rear of the building.
(c) Without restricting the permissible limits of the applicable zoning
district, the height and scale of each building shall be compatible with
its site and existing or adjoining buildings.
The maximum height for a pitched roof in the CD2 District is 45 ft. The maximum
height for a flat roof is 35 ft. The proposed structure will be 34 ft. 3 112" to the top
of the pitched stairwell roof. The flat roof will be 24 ft. high. Therefore, the
proposed addition complies with the height requirements of the CD2 District.
(d) Newly installed utility services and service modifications necessitated
by exterior alterations or building expansions shall, to the extent
feasible, be underground.
Pursuant to Section 15.13(E) of the Land Development Regulations, any new
utility lines, services, and service modifications shall be underground.
(e) The DRB shall encourage the use of a combination of common
materials and architectural characteristics, landscaping, buffers,
screens and visual interruptions to create attractive transitions
between buildings of different architectural styles.
The proposed project complies with the Design Review approval (#DR-02-19) from
January 28, 2003.
(f) Proposed structures shall be related harmoniously to themselves, the
terrain, and to existing buildings and roads in the vicinity that have a
visual relationship to the proposed structures.
The proposed project complies with the Design Review approval (#DR-02--19) frorn
January 28, 2003.
Site plan applications shall meet the following specific standards as set forth in
Section 14.07 of the South Burlinaton Land Development Reaulations:
(a) The reservation of land may be required on any lot for provision of
access to abutting properties whenever such access is deemed
necessary to reduce curb cuts onto an arterial of collector street, to
provide additional access for emergency or other purposes, or to
improve general access and circulation in the area.
It is not necessary to require any additional access easements as part of the
proposed project.
(b) Electric, telephone and other wire -served utility lines and service
connections shall be underground. Any utility installations remaining
above ground shall be located so as to have a harmonious relation to
neighboring properties and to the site.
Pursuant to Section 15.13(E) of the Land Development Regulations, any new
utility lines, services, and service modifications shall be underground.
(c) All dumpsters and other facilities to handle solid waste, including
compliance with any recycling or other requirements, shall be
accessible, secure and properly screened with opaque fencing to
ensure that trash and debris do not escape the enclosure(s).
The plans show an adequately screened dumpster on the northwesterly corner of
the subject property.
(d) Landscaping and Screening Requirements
Pursuant to Table 13-9 of the Land Development Regulations, the proposed project
will require a minimum of $10,500 of landscaping. The application states that
$10,500 of landscaping will be planted on the site, plus 12,000 will be dedicated to
the roof garden. The Board feels that this is sufficient. However, pursuant to
Section 13.06(G) of the Land Development Regulations, the applicant must submit
a landscape budget indicating the value of the proposed landscaping. This budget
shall be prepared by a landscape architect or landscape professional. The budget
will give the Development Review Board sufficient information to determine if the
minimum landscaping requirement is being met.
Pursuant to Section 13.06(B) of the Land Development Regulations, snow
storage areas must be specified and located in an area that will minimize the
potential for run-off. The plans do not depict proposed snow storage areas.
Lighting
The applicant proposes using 100W recessed can lights, two wall mounted
exterior light fixtures, and one 12 ft. Lumec "New Westminster" light within the
project parking lot. The DRC requested that the soffit lights be reduced in
wattage such that the illumination at the sidewalk not exceed 5 foot candles. The
DRB agrees that illumination at the sidewalk should not exceed 5 foot candles.
Access/Circulation
Vehicular access to the site will remain unchanged. Pedestrian access will be
enhanced with new sidewalks and inviting site design elements as discussed
above.
No changes to the existing traffic circulation patterns are proposed.
Traffic
According to the ITE, 7th Edition, the proposed 2,089 square foot medical office
(LU: 720) addition is estimated to increase traffic on the subject property by 7.77
P.M. peak -hour vtes. The additional two (2) residential dwelling units (LU: 220) is
estimated to increase traffic on the subject property by 1.24 P.M. peak -hour
vtes. So, the proposed project is estimated to generate an additional 9.01 P.M.
peak hour vies.
DECISION
Motion by 60�6
M , seconded by ( 114
to approve Site Plan application #SP-04-31 of Bill Michaud subject to the
following conditions:
1) All previous approvals and stipulations, which are not superseded by this
approval, shall remain in effect.
2) This project shall be completed as shown on the plans submitted by the
applicant, as amended by this decision, and on file in the South Burlington
Department of Planning and Zoning.
3) The plan shall be revised to show the changes below and shall require
approval of the Administrative Officer. Three (3) copies of the approved
revised plan shall be submitted to the Administrative Officer prior to permit
issuance:
a) The plans shall be revised to clearly depict designated snow storage
areas.
4) Pursuant to Section 15.13(E) of the Land Development Regulations, any new
utility lines, services, and service modifications shall be underground.
5) Prior to site plan approval, the applicant shall submit a landscape budget,
prepared by a landscape architect or landscape professional, that indicates the
minimum landscaping requirement is being met.
6) The applicant shall post a landscape bond for $10,500, prior to issuance of a
zoning permit. This bond shall remain in effect for three (3) years to assure
that the landscaping has taken root and has a good chance of surviving.
7) The Development Review Board approves a total of 23 parking spaces on the
subject property.
8) For the purpose of calculating road impact fees under the South Burlington
Impact Fee Ordinance, the Development Review Board estimates that the
expansion will generate 9.01 additional vehicle trip ends during the P.M. peak
hour.
9) If necessary, the applicant shall obtain wastewater allocation approval from
the Director of Planning and Zoning, Juli Beth Hinds, prior to issuance of a
zoning permit.
10)The applicant shall obtain a zoning permit within six (6) months pursuant to
Section 17.04 of the Land Development Regulations or this approval is null
and void.
11)The applicant shall obtain a Certificate of Compliance/Occupancy from the
Administrative Officer prior to the use of the newly converted space.
12)Any change to the site plan shall require approval by the South Burlington
Development Review Board.
Chuck Bolton e nay/abstain/not present
Mark Boucher
- ye nay/abstain/not present
John Dinklage
a nay/abstain/not present
Roger Farley —
stain/not present
Michele Kupersnay/abstain/not
present
Larry Kupferma
Wenay/abstain/notpresent
Gayle Quimby
—bstain/not present
Motion carried by a vote of I -y - ci
Signed this / day of September, 2004 by
�i
ohn Dinklage, Chair '
Please note: You have the right to appeal this decision to the Vermont
Environmental Court, pursuant to 24 VSA 4471 and VRCP 76 in writing, within 30
days of the date this decision is issued. The fee is $225.00. If you fail to appeal
this decision, your right to challenge this decision at some future time may be lost
because you waited too long. You will be bound by the decision, pursuant to 24
VSA 4472 (d) (exclusivity of remedy; finality).