HomeMy WebLinkAboutSP-07-85 - Decision - 0000 Quarry Hill Road#SP-07-85
CITY of SOUTH BURLINGTON
DEPARTMENT of PLANNING & ZONING
RALPH DESLAURIERS, JR, LOT 2
SITE PLAN APPLICATION #SP-07-85
FINDINGS of FACT AND DECISION
Ralph Deslauriers, Jr., hereafter referred to as the applicant, is requesting site plan
approval to construct one (1) 32-unit multi -family dwelling on a 1.85 acre lot, Quarry Hill
Road.
The South Burlington Development Review Board held a public hearing on December 11,
2007. Skip McClellan represented the applicant.
Based on testimony provided at the above mentioned public hearing and the plans and
supporting materials contained in the document file for this application, the Development
Review Board finds, concludes, and decides the following:
FINDINGS OF FACT
1. The applicant is requesting site plan approval to construct one (1) 32-unit multi -family
dwelling on a 1.85 acre lot, Quarry Hill Road.
2. The owner of record is Cupola Golf Course, Inc.
3. The subject property contains 1.85 acres and is located in the Residential 12 Zoning
District.
4. The plans consist of a five (5) page set of plans, page one (1) entitled, "Quarry Hill
Subdivision South Burlington Vermont Site Plan QHC-Lot #2", prepared by Llewellyn -
Howley, Inc., dated 10/25/07, last revised on 10/25/07.
-1-
Zoning District & Dimensional Requirements
Table 1. Dimensional Requirements
R12 Zoning District
Required
Proposed
Min. Lot Size
3,500 SF
1.85 acres
A Max. Density
12 units/acre
3.74 units/acre
�l Max. Building Coverage
40%
11.2%
Max. Total Coverage
60%
25.2%
Min. Front Setback
30 ft.
±30 ft.
�l Min. Side Setback
10 ft.
>10 ft.
Min. Rear Setback
30 ft.
>30 ft.
+ Max. Building Height
40 ft.
56 ft. 2 in.
zoning compliance
a. waiver required pursuant to Section 3.07(F)(2) of the Land
Development
Regulations
The coverage calculations listed in Table 1 are based on the entire 25.67 acre PUD,
including existing and previously approved development.
SITE PLAN REVIEW STANDARDS
Pursuant to Section 14.03(A)(6) of the South Burlington Land Development Regulations, any
PUD shall require site plan approval. Section 14.06 of the South Burlington Land
Development Regulations establishes the following general review standards for all site plan
applications:
The site shall be planned to accomplish a desirable transition from structure to site,
from structure to structure, and to provide for adequate planting, safe pedestrian
movement, and adequate parking areas.
The proposed project accomplishes a desirable transition from structure to site and from
structure to structure. The site provides for adequate planting and safe pedestrian
movement.
According to Table 13-1 of the South Burlington Land Development Regulations, the
proposed project will require 72 parking spaces (2 parking spaces per dwelling unit plus 1
parking space for every 4 dwelling units). A total of 72 parking spaces are proposed for the
subject building: 25 underground parking spaces, 33 aboveground parking spaces, and 14
overflow parking spaces on the adjacent lot (Quarry Hill Club).
2
According to Table 13-7 of the South Burlington Land Development Regulations, the
proposed project will require three (3) handicapped -accessible parking spaces. These three
(3) handicapped -accessible parking spaces are depicted on the plans.
The proposed parking lots conform to the Parking Lot Dimension Requirements, as outlined
in Section 13-8 of the South Burlington Land Development Regulations.
Parking shall be located to the rear or sides of buildings to the greatest extent
practicable.
The proposed project contains three (3) parking areas. One is located on the southerly side
of the proposed building, one (1) is located on the northerly side of the proposed building,
and one (1) is located under the proposed building, resulting in 25 parking spaces under the
building and 33 surface parking spaces. In addition, there is a parking lot across the street
that serves the Quarry Hill Club, which has 14 parking spaces designated for the subject
building.
Without restricting the permissible limits of the applicable zoning district, the height
and scale of each building shall be compatible with its site and existing or adjoining
buildings.
The height of the proposed building is 56'2" above average pre -construction grade. The
maximum height for buildings with peaked roofs in South Burlington is 40'. Therefore, the
applicant must obtain waiver of 16'2". Pursuant to Section 3.07(F)(2) of the Land
Development Regulations, for structures proposed to exceed the maximum height for
structures specified in Section 3.07(D) of the Land Development Regulations, as part of a
planned unit development or master plan, the DRB may waive the requirements of this
section as long as the general objectives of applicable zoning district are met. A request for
approval of a taller structure shall include the submittal of a plan(s) showing the elevations
and architectural design of the structure, pre -construction grade, post -construction grade,
and height of the structure. Such plan shall demonstrate that the proposed building will not
detract from important public scenic views from adjacent public roadways and other public
rights -of -way.
The applicant has submitted building elevation plans that indicate the pre -construction grade
and the post -construction grade for the subject property.
Newly installed utility services and service modifications necessitated by exterior
alterations or building expansions shall, to the extent feasible, be underground.
Pursuant to Section 15.13(E) of the South Burlington Land Development Regulations, any
new utility lines shall be underground.
The DRB shall encourage the use of a combination of common materials and
architectural characteristics, landscaping, buffers, screens and visual interruptions to
create attractive transitions between buildings of different architectural styles.
3
This criterion is being met.
Proposed structures shall be related harmoniously to themselves, the terrain, and to
existing buildings and roads in the vicinity that have a visual relationship to the
proposed structures.
This criterion is being met.
Site plan applications shall meet the following specific standards as set forth in Section 14.07
of the South Burlington Land Development Requlations:
The reservation of land may be required on any lot for provision of access to abutting
properties whenever such access is deemed necessary to reduce curb cuts onto an
arterial of collector street, to provide additional access for emergency or other
purposes, or to improve general access and circulation in the area.
The layout of the proposed project would create a total of five (5) curb -cuts between Quarry
Hill Club Lot #2, Quarry Hill Club Lot #3, and Larkin Lot #1. The applicant has designed the
parking layout to create a shared access between the surface parking lot of the proposed
project and the surface parking lot to south of the building on Larkin Lot #1.
Electric, telephone and other wire -served utility lines and service connections shall be
underground. Any utility installations remaining above ground shall be located so as
to have a harmonious relation to neighboring properties and to the site.
Pursuant to Section 15.13(E) of the South Burlington Land Development Regulations, any
new utility lines shall be underground.
All dumpsters and other facilities to handle solid waste, including compliance with
any recycling or other requirements, shall be accessible, secure and properly
screened with opaque fencing to ensure that trash and debris do not escape the
enclosure(s).
The plans depict an adequately screened dumpster in the northeasterly corner of the
proposed parking area to the north of the proposed building.
Landscaping and Screening Requirements
Pursuant to Section 13.06(A) of the proposed Land Development Regulations, landscaping
and screening shall be required for all uses subject to site plan and PUD review.
According to the applicant, the proposed project will cost approximately $1,920,000. Based
on this number, and in accordance with Table 13-9 of the South Burlington Land
Development Regulations, the minimum landscaping requirement is $26,700. The applicant
has submitted a landscape plan and budget prepared by Green Mountain Earth Care, which
10
are in compliance with Section 13.06 of the Land Development Regulations. The landscape
budget indicates that only $23,974 worth of new landscaping will be planted on the site.
There is a variety of existing landscaping along the southerly boundary of the site, which the
applicant is seeking to obtain a credit of $2793 for. This credit is supported, which would
bring the applicant's total landscape budget to $26,713.
Pursuant to Section 13.06(B) of the Land Development Regulations, in all off-street
parking area with twenty (20) of more parking spaces, at least ten percent (10%) of the
interior of the parking area shall be landscaped with trees, shrubs, and other plants. At
least one (1) major deciduous shade tree, whose caliper is equal to or greater than two
and one-half (2.5) inches when measures six (6) inches above ground at the time of
planting, shall be provided within each parking area for every three thousand (3,000)
square feet of paved area or every ten (10) parking spaces, whichever is greater.
The parking area to the north of the proposed building must meet this requirement, as it
contains twenty-six (26) parking spaces. The landscape plans prepared by Green
Mountain Earth Care depict adequate plantings in this parking area.
Pursuant to Section 13.06(B) of the Land Development Regulations, snow storage area
must be specified and located in an area that will minimize the potential for run-off.
The plans depict adequate snow storage areas for the northerly parking area, but not for the
southerly parking area.
Pursuant to Section 13.06(C)(1) of the South Burlington Land Development Regulations, any
dumpsters and utility cabinets on the site should be effectively screened to the approval of
the Development Review Board.
The plans depict and adequately screened dumpster to the north of the proposed building.
The City Arborist reviewed the final plat plans and provided comments in a letter dated June
30, 2004.
Access
Access to the proposed building is proposed via two (2) 30' wide curb -cuts along the
proposed public road. One (1) curb -cut serves the eight (8) parking spaces to the south of
the proposed building. The other curb -cut is shared access with the building to the north and
serves the twenty-six (25) surface parking spaces to the north of the proposed building and
the twenty-four (25) underground parking spaces. Staff has some concerns regarding the 30'
wide curb -cut serving only eight (8) parking spaces, but this seems to be the be the only
practical option for serving a parking area to the south of the proposed building.
Interstate Highway Overlay District (IHO)
All of the proposed development on the subject property is located outside of the 150' wide
buffer created by the Interstate Highway Overlay District.
5
DECISION
Motion by Gayle Quimby, seconded by Mark Behr, to approve Final Plat Application
#SD-04-40 of Ralph Deslauriers, Jr., subject to the following conditions:
1. All previous approvals and stipulations shall remain in full effect, except as amended
herein.
2. This project shall be completed as shown on the plans submitted by the applicant, as
amended by this decision, and on file in the South Burlington Department of Planning &
Zoning.
3. The applicant shall comply with the requests of the South Burlington Water Department,
as outlined in the letter from Jay Nadeau, dated June 9, 2004, prior to permit issuance.
4. The applicant shall comply with the requests of the South Burlington Fire Department, as
outlined in the letter from Chief Brent dated July 1, 2004.
5. The applicant shall comply with the requests of the City Engineer, as outlined in his letter
dated June 10, 2004, prior to permit issuance.
6. The proposed project shall adhere to standards for erosion control as set forth in Section
16.03 of the South Burlington Land Development Regulations. In addition, the grading plan
shall meet the standards set forth in Section 16.04 of the South Burlington Land
Development Regulations.
7. The applicant shall comply with the traffic mitigation measures identified during the
meeting between staff and the applicant on March 10, 2004, as outlined in the memorandum
from Juli Beth Hoover dated March 10, 2004. The applicant shall post a bond, prior to
issuance of a zoning permit, sufficient to cover the cost share of the required improvements
for a period of four (4) years, or until such time as the improvements are constructed. The
timing of construction shall be determined by the Director of Public Works, the applicant, and
the University of Vermont.
8. Pursuant to Section 15.13(E) of the South Burlington Land Development Regulations, any
new utility lines shall be underground.
9. The applicant shall post a $26,700 landscape bond prior to the issuance of the zoning
permit. This bond shall remain in effect for three (3) years to assure that the landscaping
has taken root and has a good chance of surviving.
10. Pursuant to Section 15.08(D) of the South Burlington Land Development Regulations,
the applicant shall submit homeowner's association legal documents prior to the issuance
of the zoning permit. The documents that include language that:
a) prohibits clearing or disturbance of land within wetlands or wetland buffers;
b) recreational vehicle parking will be prohibited on the property;
AND
0
c) ensures that the association shall assume all maintenance responsibilities for
the stormwater drainage facilities until such time as a future City stormwater
utility accepts the stormwater infrastructure.
11. Pursuant to Section 3.07(F)(2) of the Land Development Regulations, the
Development Review Board grants the applicant a 16'2" height waiver for the building at
264 Quarry Hill Road, for a total building height of 56'2" from average pre -construction
grade.
12. The applicant shall obtain a zoning permit within six (6) months pursuant to Section
17.04 of the Land Development Regulations or this approval will become null and void.
13. The applicant shall obtain a Certificate of Occupancy/Compliance from the
Administrative Officer prior to the occupancy of the building.
14. Any change to the final plat plans shall require approval of the South Burlington
Development Review Board or the South Burlington Administrative Officer.
Mark Behr ye /nay/abs in/not present
Matthew Birminpye,
e /nay/abstain/not present
John Dinklage nay/abstain/not present
Roger Farley — ea/nay/abstain of presen
Eric Knudsen — Pea
y/abstain/not present
Peter Plumeau —nay/abstain/not present
Gayle Quimby —ay/abstain/not present
Motion carried by a vote of 'C"
Signed this f ( day of 2) 'Q-4_- 2007, by
John Din lage, Chai
Please note: You have the right to appeal this decision to the Vermont Environmental
Court, pursuant to 24 VSA 4471 and VRCP 76 in writing, within 30 days of the date this
decision is issued. The fee is $225.00. If you fail to appeal this decision, your right to
challenge this decision at some future time may be lost because you waited too long. You
will be bound by the decision, pursuant to 24 VSA 4472 (d) (exclusivity of remedy; finality).
7