HomeMy WebLinkAboutSD-07-79 SD-07-80 - Decision - 0080 Bartlett Bay RoadCITY OF SOUTH BURLINGTON
DEPARTMENT OF PLANNING AND ZONING
ROBERT A. & MARY ALICE IRISH - BARTLETT BAY ROAD
PRELIMINARY PLAT APPLICATION #SD-07-79
FINAL PLAT APPLICATION #SD-07-80
Bob & Mary Alice Irish, hereafter referred to as the applicants, are seeking preliminary
and final plat approval of a proposal to subdivide a 3.8 acre parcel developed with a
single family dwelling into two (2) lots of 1.65 acres (lot A) and 2.15 acres (lot B), 80
Bartlett Bay Road.
The Development Review Board held a public hearing on Tuesday, January 8, 2008.
Bob Irish was present at the meeting.
Based on testimony provided at the above mentioned public hearing and the plans and
supporting materials contained in the document file for this application, the Development
Review Board hereby finds, concludes, and decides the following:
FINDINGS OF FACT
1) The applicants are seeking preliminary and final plat approval of a proposal to
subdivide a 3.8 acre parcel developed with a single family dwelling into two (2)
lots of 1.65 acres (lot A) and 2.15 acres (lot B), 80 Bartlett Bay Road.
2) The owners of record of the subject property are Michael Sirotken & Sally Fox.
3) The subject property lies in the Lakeshore Neighborhood Zoning District,
Residential 1- Lakeview Zoning District.
4) The plans submitted consist of a two (2) page set of plans, page one (1) entitled,
"Sirotkin/Fox Subdivision South Burlington Vermont", prepared by Llewellyn -
Howley, Inc., dated Nov 2007, last revised on 12/10/07.
I
I
Zoning District & Dimensional Requirements
The subject property is proposed to be subdivided into two different zoning districts.
Table 1. Dimensional Requirements
LN Zoning District
Required
Proposed
Proposed
Parcel A
Parcel B
Min. Lot Size
12,000 SF
1.65 acres
2.15 acres
Maximum Building
Coverage
20%
6%
TBD
qMaximum Overall
Coverage
40%
32%
TBD
q zoning compliance
RI -Lakeview Zoning
District
Required
Proposed
Proposed
Parcel A
Parcel B
�l Min. Lot Size
14,000 SF
1.65 acres
2.15 acres
�l Maximum Building
Coverage
15%
6%
TBD
4 Maximum Overall
Coverage
25%
32%**
TBD
** The majority of Parcel A is located within the less restrictive LN Zoning District. For
purposes of simplicity, coverage is being assessed for the whole of each parcel and not
as each portion relates to each zoning district. Overall coverages are higher for Parcel A
simply because Bartlett Bay Road, privately owned by the property owner, is being
considered towards this coverage. The building and overall coverages are being
respected for each lot, for each zoning district.
TBD- No development proposed at this time. Coverages must respect the zoning district
limitations and will be assessed as zoning permits are requested and reviewed.
SUBDIVISION CRITERIA
Pursuant to Section 15.18 of the South Burlington Land Development Regulations,
subdivisions shall comply with the following standards and conditions:
Sufficient water supply and wastewater disposal capacity is available to meet the
needs of the project.
There are no new buildings or associated infrastructure proposed for this property as part of
this application.
According to Section 15.13 of the South Burlington Land Development Regulations,
the subdivider or developer shall connect to the public sewer system or provide a
community wastewater system approved by the City and the State in any
subdivision where off -lot wastewater is proposed.
The preliminary and final plat plans should be revised to show the water line easement for
the water line on the applicant's property.
Sufficient grading and erosion controls will be utilized during and after construction
to prevent soil erosion and runoff from creating unhealthy or dangerous conditions
on the subject property and adjacent properties.
Sufficient grading and erosion controls shall be utilized during and after construction to
prevent soil erosion and runoff from creating unhealthy or dangerous conditions on the
subject property and adjacent properties.
The project incorporates access, circulation, and traffic management strategies
sufficient to prevent unreasonable congestion of adjacent roads.
The existing lot is currently accessed via Bartlett Bay Road. The applicant is proposing to
access the new lot B via Lakeview Lane, a private road. At this time, there are already three
(3) homes accessed via Lakeview Lane, the maximum for a private road. The applicant
shall be required to upgrade Lakeview Lane to a public road, meeting all related public
roadway standards prior to the issuance of a zoning permit for the development of Lot B.
The plans reflect a public roadway and have been reviewed by the City Engineer and the
South Burlington Director of Public Works. The applicant is requesting to modify the public
roadway standards to reduce the width of the pavement to 20 feet, with no curbs or
sidewalk.
The project's design respects and will provide suitable protection to wetlands,
streams, wildlife habitat as identified in the Open Space Strategy, and any unique
natural features on the site.
The City's Official Wetland Map does not indicate any wetlands on the subject property. If
there are any, the applicant shall include these on the site plans.
There is no adverse impact to the wetlands as a result of this application.
The project is designed to be visually compatible with the planned development
patterns in the area, as specified in the Comprehensive Plan and the purpose of the
zoning district(s) in which it is located.
The applicant has noted that the newly created lot will be targeted for residential
development at some future point. The proposed subdivision is compatible with the
planned development patterns of the R1-Lakeview Zoning District, as outlined in Section
9.01 of the Land Development Regulations.
Open space areas on the site have been located in such a way as to maximize
opportunities for creating contiguous open spaces between adjoining parcels and/or
stream buffer areas.
There are no new buildings proposed for this property as part of this application.
The layout of a subdivision or PUD has been reviewed by the Fire Chief or (designee)
to ensure that adequate fire protection can be provided.
This application does not warrant review by the Fire Chief.
Roads, recreation paths, stormwater facilities, sidewalks, landscaping, utility lines
and lighting have been designed in a manner that is compatible with the extension of
such services and infrastructure to adjacent landowners.
As stated above, Lakeview Lane must be upgraded to public roadway standards before
any development may be commenced on Lot B.
Roads, utilities, sidewalks, recreation paths, and lighting are designed in a manner
that is consistent with City utility and roadway plans and maintenance standards.
As stated above, Lakeview Lane must be upgraded to public roadway standards as herein
modified before any development may be commenced on Lot B.
The project is consistent with the goals and objectives of the Comprehensive Plan
for the affected district(s).
The proposed subdivision is in conformance with the South Burlington Comprehensive
Plan.
Other
The survey plat contains multiple references to the Town of Georgia. The plat should be
revised to remove all such references and shall instead refer to the City of South
Burlington.
The City Engineer reviewed the plans and provided comments in a memo dated December
27, 2007. The Board supports all recommendations with the exception of item number 1, in
reference to City ownership of Bartlett Bay Road. The City does not wish to accept this road
unless it is upgraded to City standards. Such a matter is not considered as part of this
application or review. The applicant shall adhere to the other comments of the City
Engineer. Where applicable the plans shall be revised to adhere to said comments. The
Director of Public Works concurs on this matter and supports all other items noted by the
City Engineer.
DECISION L
Motion by G �-� u , seconded by T/F LE
to approve Preliniinary Plat Appli tion #SD-07-79 and Final Plat Application #S -07-80
of Robert A. & Mary Alice Irish, subject to the following conditions:
All previous approvals and stipulations shall remain in full effect, except as
amended herein.
2. This project shall be completed as shown on the plat submitted by the applicants
and on file in the South Burlington Department of Planning and Zoning.
3. The plans shall be revised to show the changes below and shall require approval
of the Administrative Officer. Three (3) copies of the approved revised plans shall
be submitted to the Administrative Officer prior to recording.
a. The preliminary and final plat plans shall be revised show the water line
easement for the water line on the applicant's property.
b. The survey plat shall be revised to remove all references to the Town of
Georgia and their Planning Commision and shall instead refer to the City of
South Burlington and the Development Review Board.
c. The plans shall be revised to comply with the requests of the City Engineer
as outlined in a memorandum dated December 27, 2007.
4. The applicant shall adhere to the comments of the City Engineer with exception to
item number 1, as outlined in a memorandum dated December 27, 2007.
5. Sufficient grading and erosion controls shall be utilized during and after construction
to prevent soil erosion and runoff from creating unhealthy or dangerous conditions
on the subject property and adjacent properties.
6. The applicant shall upgrade Lakeview Lane to the modified city roadway standards
prior to issuance of a zoning permit for any land development on proposed 'Lot B'.
7. The Board approves a reduction in pavement width for Lakeview Lane to 20 ft width
with no curbs or sidewalk.
8. Prior to the start of construction of Lakeview Lane, the applicant shall post a bond
which covers the cost of said improvements.
9. Prior to the issuance of a zoning permit to construct Lakeview Lane, the applicant
shall post an $8300 bond for the street trees. This bond shall remain in effect for
three (3) years after the trees have been planted to assure that the trees have taken
root and have a good chance of surviving.
10. Any changes to the final plat plan shall require approval by the South Burlington
Development Review Board.
11. The final plat plan (survey plat) shall be recorded in the land records within 180
days or this approval is null and void. The plan shall be signed by the Board
Chair or Clerk prior to recording. Prior to recording the final plat plan, the
applicants shall submit a copy of the survey plat in digital format. The format of
the digital information shall require the approval of the South Burlington GIS
Coordinator.
Mark Behr — yea/nay/abstain not rese
Matthew Birming m — yea/nay/abstai not present
John Dinklage a nay/abstain/not presen
Roger Farley nay/abstain/not present
Eric Knudsen ye /nay/abstain/not resent
Peter Plumeau — /nay/abstain en of pres
Gayle Quimby —&nay/abstain/no present
Motion carried by a vote of �- - 6)
Signed this S/day of 2008, by
inklage, C
Please note: You have the right to appeal this decision to the Vermont Environmental
Court, pursuant to 24 VSA 4471 and VRCP 76 in writing, within 30 days of the date this
decision is issued. The fee is $225.00. If you fail to appeal this decision, your right to
challenge this decision at some future time may be lost because you waited too long.
You will be bound by the decision, pursuant to 24 VSA 4472 (d) (exclusivity of remedy;
finality).