BACKGROUND:
This application proposes construction of a four story mixed use building having a
gross floor area of 132,420 square feet, plus a 33,105 square feet parking garage at
the basement level. A total of 120 residential units are proposed, comprised of 76
studio and one bedroom dwellings, and 44 two bedroom dwellings. In addition to
residential support functions, there will be two separate non-residential spaces at
street level. An 1,800 square feet space is planned for either a café or similar private
use for residents. A 5,000 square feet day care use is planned to serve residents
within this and adjacent buildings.
Site Plan application #SP-22-033 was approved on August 30, 2022 for the
construction of 131 residential units and 1,800 square feet of commercial space.
This amendment application involves the addition of the day care and outside play
space, a slight reduction in the footprint of the building, and adjustments to the site
layout to accommodate these changes. Construction of the building and site
improvements will be completed as a single phase of work.
The replacement of dwelling units on the first floor with the proposed day care use
has lead to minor changes in the Garden Street elevation – primarily related to door
locations.
SITE:
The building will be constructed on Lots M1, M2 & M3 located within South
Burlington’s T-4 City Center zoning district. The site is located on the south side of
Garden Street, adjacent to the Healthy Living Market / Trader Joes / Pier 1
commercial complex just off Dorset Street. The site is currently undeveloped and
was mostly cleared in late 2018 in preparation for development. Since then, small
shrubs and saplings have regrown across most of the site.
CONSTRUCTION PHASING:
This application proposes construction of the entire building and site improvements
in a single phase.
REGULATED ELEVATION GLAZING:
To comply with the building envelope standards, a minimum of 75% of the first
story glazing along Garden Street will be transparent, and a minimum of 85% of the
upper story glazing along Garden Street will be transparent. It is likely that 100% of
the glazing on the first and upper stories along Garden Street will be transparent. If
less than 100% of the glazing on the first story and upper stories is transparent, the
Applicant will demonstrate compliance with the applicable minimum standards
prior to issuance of a certificate of occupancy.
PARKING:
A parking garage at the basement level will provide 87 spaces. An additional 75
surface spaces are proposed, for a total of 162 parking spaces (or 1.35 parking
spaces per dwelling unit). The surface parking area complies with the 10% parking
lot island landscaping requirement. While there are no parking requirements for
commercial uses, parking for pick-up and drop off will be available in the lot at the
rear of the building and in the on-street spaces on Garden Street. However, it is
anticipated that the day care will serve those in the City Center area, reducing the
need for parking.
Short term bike parking (16 spaces on 8 inverted U racks) is provided in three
locations near the building entrances adjacent to the parking lot. Long term bike
parking is provided in the parking garage. Bike parking will be located at the front
of the vehicle parking spaces, as well as common areas within the garage. A vertical
bike rack will be wall mounted, staggered between vehicle parking spaces (the
vehicle space and bike space will be assigned to the same resident). The balance of
the long term bike spaces (28 bike spaces) will be provided in common areas using
vertical wall mounted racks. A total of 148 long term bike spaces will be provided
for the 120 dwelling units and non-residential uses.
OPEN SPACE:
The open space requirement will be met using a combination of onsite and offsite
open space elements. The Large Development Area open space credit utilizing the
City Stormwater Park located off Market Street will be used to meet 45% of the open
space requirement. The balance of the required open space will be provided in a
pocket park at the west end of the building, adjacent to Garden Street.
INCLUSIONARY / AFFORDABLE HOUSING:
Miscellaneous Application #MS 18-05 established compliance with inclusionary
zoning requirements for current and future residential development within the
Covered Development, which includes Lots M1, M2, & M3. The proposed building
involves construction of 120 market rate dwelling units. Inclusionary housing units
are not required for this application, based upon the findings for the Covered
Development in the Miscellaneous Application approval. As required by conditions
10, 11, & 13 of the approval, an updated summary of the inclusionary and market
rate units including this application is attached.
WATER & WASTEWATER FLOWS:
For the 120 residential units (76 one bedroom & 44 two bedroom units), the water
and wastewater design flow is 19,880 GPD and the wastewater design flow is
22,960 GPD.
The day care is estimated to have a maximum of 78 children and 12 staff (with no
meals prepared onsite). The day care water and wastewater design flow is 1,170
GPD.
The water and wastewater design flow for the cafe will be calculated once a tenant
is known and the design criteria are defined.
STORMWATER:
Gravel wetland 5 (GW5) was previously constructed on the west side of the
proposed building, south of the open space. Runoff from the new parking lot will be
directed to catchbasins and piped to the stormwater collection system along Garden
Street, which discharges to GW5. Rooftop runoff from the portion of the building
adjacent to GW5 will be piped directly to the gravel wetland. Other than the
installation of the rooftop runoff pipe, there are no proposed modifications to GW5.
Rooftop runoff from the portion of the building adjacent to Garden Street will be
directed to the infiltration system located on Lot M5, near the southeast corner of
the parking lot, behind the trash enclosure. Since the rooftop runoff is not
commingled with surface runoff, no pretreatment is required.
Note that the total proposed impervious surface has been slightly reduced from the
prior application (from 1.95 acres to 1.91 acres impervious surface). The reduction
in impervious surface is due to the revised building footprint and corresponding
reconfiguration of the garage acccess.
The proposed stormwater design has remained unchanged from that approved in Site
Plan application #SP-22-033.
TRAFFIC IMPACT FEES:
The Applicant requests that the approval of this application include a
recommendation that the City Council approve a credit against the traffic impact fee
for the value of the ‘in-kind’ contribution associated with the construction of Garden
Street.
Approved Site Plan #SP-20-009 estimates the cost of construction of the segment of
Garden Street from Market Street to the existing box culvert to be $1,838,000. A
portion of this ‘in-kind’ contribution has previously been applied to other
applications.